Question 8.48: Figure 8.115 shows speed (frequency)-load characteristics of...

Figure 8.115 shows speed (frequency)-load characteristics of two generators supplying in parallel a load of 2.8 MW at 0.8 pf lagging:

(a) At what frequency is the system operating and what is the load supplied by each generator?

(b) If the load is now increased by 1 MW, what will be the frequency and the load sharing?

(c) In part (b) which should be the set point of G_{2}, for the system frequency to be 50 Hz? What would be the load sharing now?

The Blue Check Mark means that this solution has been answered and checked by an expert. This guarantees that the final answer is accurate.
Learn more on how we answer questions.

The speed-load characteristics of the two generators are drawn in Fig. 8.116 on the sides of the load axis. These being linear can the represented by the equation of a line as

y = mx + c

where

x = generator load, it is taken positive on both sides

y = system frequency, same for both generators

c = set frequency (on frequency axis)

m = slope, Hz/MW

On the figure

AB = total load, \left(x_{1}+x_{2}\right)

AC = x_{1} , , load supplied by G1

BC = x_{2}, load supplied by G2

OC = system frequency

(a) Substituting values.

G_{1}                              y=-x_{1}+51.8 \text { (i) }   m = – 1 Hz/MW

G_{2}                                y=-x_{2}+51 m = – 1 Hz/MW

It follows

-x_{1}+51.8=-x_{2}+51

Or                                        \left(x_{1}-x_{2}\right)=0.8                                                  (iii)

Solving                                      x_{1}+x_{2}=2.8 MW (total load, AB)

Load supplied by G_{1} ;                         x_{1}=1.8 MW

Load supplied by G_{2} ;                       x_{2}=1 MW

System frequency.                  f=y=-1.8+51.8=50 Hz

(b) Load increased by 1 MW

x_{1}+x_{2}=2.8+1=3.8 MW                                                  (iv)

Solving Eqs (iii) and (iv)

Load G_{1} :                                            x_{1} = 2.3 MW; increase 2.3 – 1.8 = 0.5 MW

Load G_{2} :                                  x_{2} = 1.5 MW; increase 1.5 – 1 = 0.5 MW

Note: Additional load equally divided as the two characteristics have the same slope

system frequency                       f=y=-2.3+51.8=49.5 Hz

(c) The G_{1} can supply the load of 1.8 MW at the frequency of 50 Hz. The remaining power must be shared by G_{2}. So the new load of G_{2} is 2 MW. For the new load, the set point of G_{2}  must be

50=-1 \times 2+  set frequency

Set frequency = 52 Hz

8 48

Related Answered Questions