Question 16.TQ.9 : Using the data contained in the previous question, calculate...

Using the data contained in the previous question, calculate the following performance measures:

(a) efficiency ratio
(b) capacity ratio
(c) production volume ratio.

The blue check mark means that this solution has been answered and checked by an expert. This guarantees that the final answer is accurate.
Learn more on how we answer questions.

Performance measures for Anthea Ltd:

(a) Efficiency ratio:

\frac{SHP}{Actual  hours} \times 100=\frac{8000}{10000}\times 100=80\%

(b) Capacity ratio:

\frac{Actual  hours}{Budgeted  hours^{W} } \times 100=\frac{10000}{9000}\times 100=111.1\%

(c) Production volume ratio:

\frac{SHP}{Budgeted  hours^{W} } \times 100=\frac{8000}{9000}\times 100=88.9\%

 

\frac{^W 135000}{15}