Question 4.5: What is the payback period of the Chaotic Industries project...

What is the payback period of the Chaotic Industries project from Activity 4.2?

The blue check mark means that this solution has been answered and checked by an expert. This guarantees that the final answer is accurate.
Learn more on how we answer questions.

The inflows and outflows are expected to be:

Time Net cash
flows
£000
Cumulative
net cash flows
£000
Immediately Cost of vans (150) (150)
1 year’s time Saving before depreciation 30 (120)   (−150 + 30)
2 year’s time Saving before depreciation 30 (90) (−120 + 30)
3 year’s time Saving before depreciation 30 (60) (−90 + 30)
4 year’s time Saving before depreciation 30 (30) (−60 + 30)
5 year’s time Saving before depreciation 30 0 (−30 + 30)
6 year’s time Saving before depreciation 30 30 (0 + 30)
6 year’s time Disposal proceeds from the vans 30 30 (0 + 30)

The payback period here is five years; that is, it is not until the end of the fifth year that the vans will pay for themselves out of the savings that they are expected to generate.