Question 7.A.21: Now assume that Shah Ltd (Activity 7.20) has no spare capaci...
Now assume that Shah Ltd (Activity 7.20) has no spare capacity, so it can only produce the component internally by reducing its output of another of its products. While it is making each component, it will lose contributions of £12 from the other product. Should the component be subcontracted or produced internally?
The blue check mark means that this solution has been answered and checked by an expert. This guarantees that the final answer is accurate.
Learn more on how we answer questions.
Learn more on how we answer questions.
The answer is to subcontract. In this case, both the variable cost of production and the opportunity cost of lost contributions must be taken into account.
Thus, the relevant cost of internal production of each component is:
£ | |
Variable cost of production of the component | 15 |
Opportunity cost of lost production of the other product | \underline{12} |
\underline{27} |
This is obviously more costly than the £20 per component that will have to be paid to the subcontractor.
Related Answered Questions
Question: 7.A.23
Verified Answer:
The things that we could think of are as follows:
...
Question: 7.E.1
Verified Answer:
Lombard Ltd
Relevant cost of undertaking the contr...
Question: 7.RQ.4
Verified Answer:
In the face of a restricting scarce resource, prof...
Question: 7.RQ.3
Verified Answer:
Operating gearing refers to the extent of fixed co...
Question: 7.RQ.2
Verified Answer:
The BEP is the break-even point, that is, the leve...
Question: 7.RQ.1
Verified Answer:
A fixed cost is one that is the same irrespective ...
Question: 7.S-A.Q.1
Verified Answer:
Khan Ltd
(a) The break-even point, if only the A...
Question: 7.A.22
Verified Answer:
We feel that there are two major factors:
1 Gener...
Question: 7.A.20
Verified Answer:
The answer is that Shah Ltd should produce the com...
Question: 7.A.19
Verified Answer:
If the remaining three B14s were subcontracted at ...