Question 8.P.11: A public works project is proposed that has total present-wo......

A public works project is proposed that has total present-worth benefits of $75 million and total present-worth costs of $55 million. In deliberating this proposal, some members of the town council have suggested that the project has a total present-worth disbenefit of $15 million; other members feel the $15 million should be treated as a cost. How should the proposal be evaluated?

Step-by-Step
The 'Blue Check Mark' means that this solution was answered by an expert.
Learn more on how do we answer questions.

In this particular case, it makes very little difference whether the $15 million is classified as a disbenefit or as a cost. If the $15 million is treated as a disbenefit,

BCR = \frac{\$75  –  \$15}{\$55} = 1.09

If it is treated as a cost,

BCR = \frac{\$75}{\$55  +  \$15} = 1.07

However, to eliminate any confusion, (8.7) should be used:

NBV = B – D – C  (8.7)

NBV = $75 – $15 – $55 = $5 million

Since NBV > 0, the project is economically acceptable.

Related Answered Questions

Question: 8.P.5

Verified Answer:

From (8.2), NPV = -|CF_0| + A(PIA, ...
Question: 8.P.6

Verified Answer:

Try i = 15% NPV = -$50 000 + $16719(P/A, 15%, 5) =...
Question: 8.P.4

Verified Answer:

By definition, the ROR is the interest rate at whi...
Question: 8.P.1

Verified Answer:

By (8.1), NPV\ =\ -|CF_0|\ +\ \sum\limits_{...
Question: 8.5

Verified Answer:

The sum of the first three yearly cash inflows, $3...
Question: 8.P.8

Verified Answer:

Descartes' rule tells us to expect no more than th...