Question 9.2: Design a channel to carry a flow of 6.91 m³ /s. The channel ......

Design a channel to carry a flow of 6.91 m³ /s. The channel will be excavated through stiff clay at a channel bottom slope of 0.00318.

Given:

Q = 6.91 m³ /s;
S_{o} = 0.00318;
Channel material is clay.

Determine:

B_{o} = ?
Flow depth = ?

Step-by-Step
The 'Blue Check Mark' means that this solution was answered by an expert.
Learn more on how do we answer questions.

For stiff clay, n = 0.025, suggested side slope, s = 1 : 1 (from Table 9-2), and the permissible flow velocity (from Table 9-3) is 1.8 m/s. Hence,
\quad\quad\quad\quadA = 6.91 / 1.8 = 3.83 m²
Substituting values for V, n, and S_{o} into Manning equation, and solving for R, we get R = 0.713 m. Hence,
\quad\quad\quad\quad P=\frac{3.83}{0.713}=5.37m
\quad\quadSubstitution into expressions for P and A from Eq. 9-11 and equating them to the values computed above, we obtain

\quad\quad\quad\quad P=B_{o}+2\sqrt{1+s^{2}}y
\quad\quad\quad\quad A = (B_{o} + sy)y (9-11)
\quad\quad\quad\quad B_{o}+2.83y=5.37\\\quad\quad\quad\quad\quad(B_{o}+y)y=3.83
Elimination of B_{o} from these two equations yields
\quad\quad\quad\quad 1.83y² – 5.37y + 3.83 = 0
Solution of this equation gives y = 1.22 m. The freeboard from Eq. 9-1 may be calculated as \sqrt{0.8\times1.22} = 0.99 m, whereas the suggested value in Table 9-1 is 0.75 m. Let us select a freeboard of 0.75 m. Then, the depth of the section = 1.22 + 0.0.75 = 1.97 m. Select a depth of 2.0 m and bottom width of 1.9 m.
\quad\quad\quad\quad F_{b}=\sqrt{ky} (9-1)

Table 9-2 Suggested Side Slopes^{∗}
Material Side slope
Rock  Nearly vertical
Stiff clay \frac{1}{2} to 1:1
Firm soil 1:1
Loose sandy soil 2:1
Sandy loam 3:1
^{∗} After Fortier and Scobey [1926]
Table 9-3 Recommended Permissible Velocities^{∗}
Material V (m/s)
Fine sand 0.6
Coarse sand 1.2
Earth
Sandy silt 0.6
Silt clay 1.1
Clay 1.8
Grass-lined earth (slopes < 5 per cent)
Bermuda grass
Sandy silt 1.8
Silt clay 2.4
Kentucky Blue grass
Sandy silt 1.5
Silt clay 2.1
Poor rock (usually sedimentary)
Soft sandstone 2.4
Soft shale 1.1
Good rock (usually igneous or hard metamorphic) 6.1
^{∗} After U. S. Army Corps of Engineers [1970]
Table 9-1 Suggested Freeboard^{∗}
Discharge (m^3 /s) < 0.75 0.75 to 1.5 1.5 to 85 > 85
Freeboard (m) 0.45 0.60 0.75 0.90
^{∗} After Ranga Raju [1983]