Question 19.8: Single-Duct VAV Secondary System Sizing (Design or Peak Cond......

Single-Duct VAV Secondary System Sizing (Design or Peak Conditions)

A two-zone building is to be equipped with a VAV system with preheat and reheat under the load conditions noted as follows. Size the supply fan, cooling coil, preheat coil, and reheat coil (or baseboard heating) for this building. Note that these will also apply to a CAV system under peak design conditions.
Given: The following data are known from the load calculation and by the designer’s specification (these loads exclude the contribution from outdoor air):

Other:
(a) Summer design dry- and wet-bulb temperatures: 97°F and 76°F (resulting in 0.0144 lb_{w}/lb_{a} humidity ratio at peak conditions).
(b) Winter design temperature: 7°F and air assumed to be totally dry.
(c) Supply system pressure drop at full airflow: 3.0 inWG.
(d) Fan efficiency: 60%.
(e) Supply fan air temperature rise: 1°F.
(f) Return air fan air temperature* rise: none.

(g) Ventilation airow rate: 2400 ft³/min.
(h) Cooling coil outlet humidity ratio (at typical 85% RH): 0.0077 lb_{w}/lb_{a}.
(i) Zone primary supply air temperature difference ∆T_{supply}: 20°F.
(j) The maximum temperature to which space supply air can be heated is 105°F.
Figure: See Figure 19.15b.
Assumptions:
(i) Ignore factors not included in the list given earlier, such as duct heat losses and gains.
(ii) The location is assumed to be at sea level.
(iii) Rather than use enthalpy balances on the zones, the flows will be designed based
on sensible heat loads (this is meant to simplify the problem).
(iv) Peak loads are coincident; no diversity adjustment is used.
(v) During peak heating, latent loads on the space are negligible.
(vi) During winter, room humidifiers are used to maintain the necessary humidity levels.
(vii) The supply airflow to the zones cannot  be reduced to less than 60% by mass of the full-load design value by mass.
Lookup value: Outdoor-specific volume = v_{0} = 14.35  ft^{3}/lb_{a}, c_{a} = 0.24  Btu/(lb_{a}·°F), and h_{v} = 1075  Btu/lb_{w}.
Find: Coil loads (preheat, cooling, and terminal reheat) and fan size.

* The return fan heat is often less than the supply fan heat because airflow is less (local exhausts remove air locally), and return ducting via ceiling plenums has  smaller pressure drop than found in supply ducts.

Zone A (Exterior) Zone B (Interior)
Sensible peak
summer design
cooling load
\dot{Q}_{sen,A} = 224,844  Btu/h \dot{Q}_{sen,B} = 103,308  Btu/h
Latent peak summer design cooling load \dot{Q}_{lat,A} = 56,000  Btu/h \dot{Q}_{lat,B} = 20,000  Btu/h
Sensible peak winter design load \dot{Q}_{heat,A} = 143,000  Btu/h \dot{Q}_{cool,B} = 49,092  Btu/h
Zone temperature Tzone 75°F 75°F
19.15
Step-by-Step
The 'Blue Check Mark' means that this solution was answered by an expert.
Learn more on how do we answer questions.

The solution will follow the numbering system used in the preceding discussion.
1. Calculate ventilation airflow rate.

\dot{m}_{a,o} = \frac{\dot{V}_{a}}{v_{0}} = \frac{2400  cfm}{14.35  ft^{3}/lb_{a}} = 167.2  lb_{a}/min

Cooling Design Day (T_{db,0} = 97°F)
2. Determine air mass flow rates (Equation 19.11).

\dot{Q}_{space,sen} = \dot{m}_{a} \cdot c_{a} \cdot (T_{db,space}  –  T_{db,supply})                 (19.11)

\dot{m}_{a,A} = \frac{224,844  Btu/h}{0.24  Btu/(lb \cdot °F)  \times  60  min/h  \times  20°F} = 780.7  lb_{a}/min

 

\dot{m}_{a,B} = \frac{103,308  Btu/h}{0.24  Btu/(lb \cdot °F)  \times  60  min/h  \times  20°F} = 358.7  lb_{a}/min

Thus, the total airflow is \dot{m}_{a} = 1,139.4  lb_{a}/min or 14,983 ft³/min (based on cooling coil leaving condition, specific volume = 13.15  ft^{3}/lb_{a})

3. The system pressure drop is 3.0 inWG.
Therefore, the fan power is given by Equation 16.34 IP:

\dot{W} = \frac{\dot{V}_{a} \cdot \Delta P}{6,356  \times  \eta_{fan}} = \frac{14,983  ft^{3}/min  \times  3.00  inWG}{6,356  \times  0.6} = 11.8  hp

Note that this is the fan brake hp and does not include the electric motor efficiency
4. Determine cooling air supply temperature.

T_{supply} = T_{zone}  –  \Delta T_{db,supply} = 75°F  –  2°F = 55°F

5. Determine cooling coil leaving temperature.

T_{coil,out} = T_{3} = T_{supply}  –  \Delta T_{db,fan} – \Delta T_{db,duct}

= 55°F  –  1°F  –  0°F = 54°F

6. Determine zone return air condition.
According to the problem statement, there are no return duct heat gains; therefore, the return dry-bulb temperature for each zone is 75°F.
7. Compute average return air humidity and temperature.
The return air average moisture content under steady state is the given zone supply air humidity ratio (0.0077 lb_{w}/lb_{a}) increased by the total latent load:

\bar{W}_{6} = W_{3} + \frac{Q_{lat}}{\dot{m}_{a} \cdot h_{vap}} = 0.0077  lb_{w}/lb_{a}

 

+ \frac{(56,000  +  20,000)  Btu/h}{1,139.4  lb/min  \times  60  min/h  \times  1,075  Btu/lb}

 

= 0.00873  lb_{w}/lb_{a}

The average return air temperature is T_{7} = T_{9} = 75°F. This condition corresponds to an average space RH_{6} = 48% that meets human comfort criteria.
8. Compute mixed-air condition. To find the mixed-air temperature entering the cooling coil, an energy balance is performed at point 1 where the return and outside air ducts connect. Since the ventilation airow rate is 167.2 lb_{a}/min, the mixed-air temperature under design conditions is* as follows:

T_{m} = T_{9} \left\lgroup 1  –  \frac{\dot{m}_{0}}{\dot{m}_{a}} \right\rgroup + T_{0} \frac{\dot{m}_{0}}{\dot{m}_{a}} = 75.0°F \times \left\lgroup 1  –  \frac{167.2}{1139.4} \right\rgroup + 97°F \times \left\lgroup \frac{167.2}{1139.4} \right\rgroup

= 78.2°F

Likewise, the mixed-air humidity ratio is found by a water vapor mass balance:

W_{m} = 0.00873  lb_{w}/lb_{a} \times \left\lgroup 1  –  \frac{167.2}{1139.4} \right\rgroup + 0.0144  lb_{w}/lb_{a} \times \left\lgroup \frac{167.2}{1139.4} \right\rgroup = 0.0096  lb_{w}/lb_{a}

9. Compute cooling coil loads (preheat coil is inactive in summer). The coil sensible load is

\dot{Q}_{cc,sen} = \dot{m}_{a} c \Delta T_{coil} = 1139.4  lb_{a}/min \times 60  min/h \times 0.24  Btu/(lb \cdot °F) \times (78.2  –  54)°F

= 397,529  Btu/h  or  33.13  tons

The latent load is found from:

\dot{Q}_{cc,lat} = m_{a} \cdot h_{vap} \cdot \Delta W_{cc} = 1,139.4  lb_{a}/min \times 60  min/h \times 1075  Btu/lb \times (0.00957  –  0.0077 )  lb_{w}/lb_{a}

= 137,103  Btu/h = 11.45  tons

The total coil load or coil cooling rate is

\dot{Q}_{cc,tot} = \dot{Q}_{cc,sen} + \dot{Q}_{cc,lat} = 534,632  Btu/h = 44.55  tons

Heating Design Day (T_{db,0} = 7°F)
10. Determine preheat coil load. The peak load on the preheat coil is determined based on the load needed to heat the cold outdoor ventilation air on the winter design day to the nominal coil outlet temperature (54°F in this example).
Therefore, the preheat (subscript “ph”) coil size is given by (assuming that outdoor air intake is the same as under peak summer condition)

\dot{Q}_{ph} = \dot{m}_{a} c_{p} (T_{3}  –  T_{0}) = 167.2  lb_{a}/min \times 60  min/h \times 0.24  Btu/(lb_{a} \cdot °F) \times (54  –  7)°F = 113,161  Btu/h

It must, however, be noted that the preheat coil will be activated if T_{1} < 54°F and will raise the supply airstream temperature to 54°F.
11. Determine airflow rates from Equation 19.11
a. Zone A requires heating: assume maximum allowable supply air temperature of 105°F:

\dot{m}_{a,A} = \frac{143,000  Btu/h}{0.24 Btu/(lb \cdot °F) \times 60  min/h \times (105  –  75)°F}

 

= 331.0  lb_{a}/min

Recall the stipulation that minimum airflow rate should not be less than 60% of the peak, or \dot{m}_{a,min} = 0.6  \times 780.7 = 468.4  lb_{a}/min . So, we set m_{a,A} = 468.4  lb_{a}/min.
b. Zone B requires cooling: assume minimum coil set point temperature
of 54°F:

\dot{m}_{a,B} = max \left\{\begin{matrix} (0.6 \times 358.7) \\ \left[ \frac{49,902 Btu/h}{0.24 Btu/(lb \cdot °F) \times 60 min/h \times (75 – 55)°F)}\right] \end{matrix} \right.

 

= max(215.2,170.4) = 215.2  lb_{a}/min

Note that even for zone B, the stipulated minimum is reached.
Total airflow rate is 468.4 + 215.2 = 683.7  lb_{a}/min (rounded).
12. Determine supply air temperatures to the zones based on sensible heat balances.

T_{5} = T_{6} \pm \frac{\dot{Q}_{space}}{\dot{m}_{a} c_{p}}

Zone A: heating

T_{db,5A} = 75°F + \frac{143,000  Btu/h}{0.24 Btu/(lb_{a} \cdot °F) \times 60  min/h \times 468.4  lb_{a}/min}

= 96.2°F

Zone B: cooling

T_{db,5B} = 75°F  –  \frac{49,092  Btu/h}{0.24 Btu/(lb_{a} \cdot °F) \times 60  min/h \times 215.2  lb_{a}/min}

= 59.2°F

13. Determine mixed-air temperature.

T_{2} = 75.0°F \times \left\lgroup 1  –  \frac{167.2}{683.7} \right\rgroup + 7°F \times \left\lgroup \frac{167.2}{683.7} \right\rgroup = 58.4°F

Likewise, the mixed-air humidity ratio can be found assuming room air to be at the cooling coil leaving humidity ratio W_{1} = W_{3} = 0.0077  lb_{w}/lb_{a}. This is not needed, however, for our calculations, since there will not be any latent load on the coil during the winter design condition.
14. Compute cooling coil load. The needed supply air temperature to Zone B is 59.2°F (from step 12) and 1°F temperature rise by the fan, which should be taken into account. Hence, the coil leaving temperature should be 58.2°F.

\dot{Q}_{cc,sen} = 683.7  lb_{a}/min \times 60  min/h \times 0.24  Btu/(lb_{a} \cdot °F) \times (58  –  58.2)°F = 2060  Btu/h or 0.172  tons

(in practice such a small cooling load would not justify switching on the chiller)
15. Compute reheating (assuming the chiller to be activated).
Zone A:

\dot{Q}_{hc,A} = 468.4  lb_{a}/min \times 60  min/h \times 0.24  Btu/(lb_{a} \cdot °F) \times (96.2  –  59.2)°F = 249,846  Btu/h

Zone B:

\dot{Q}_{hc,B} = 215.2  lb_{a}/min \times 60  min/h \times 0.24  Btu/(lb_{a} \cdot °F) \times (59.2  –  59.2)°F = 0  Btu/h

The total peak heating requirement is the sum of the preheat and reheat amounts:

\dot{Q}_{heat,tot} = 113,161 + 249,846 + 0 = 363,007  Btu/h

This heat rate must be increased by pickup loads from night setback, safety factors, and piping losses to size the coils and the boiler.
Comments
Since this is a simple two-zone building, no diversity was assumed in the cooling or heating loads.
Although diversity is rarely taken into account in heating loads unless internal or solar gains coincide with peak heating conditions, some diversity can be assumed in cooling loads when the building consists of a larger number of zones. With two zones, it is safer not to assume any diversity.
This example shows that the secondary systems have a considerable effect on the sizing of the primary heating and cooling plants. In any building more complex than a single-family residence, the secondary system loads are usually greater (and in many instances, much greater) than space zone
loads. This effect must be considered in sizing the central plant. In this example at design conditions, the zone cooling load is about 330 kBtu/h, while the coil cooling load is 535 kBtu/h. The difference is due to the  outdoor air that is conditioned at the central air handler coil.
In this example, we have used a given value of fan temperature rise. The actual rise can be computed as discussed in Section 19.1.3. Although the return fan has not been sized in this example, it can be done exactly as it was done with the supply fan. The duct pressure drop and return fan efciency must be known to complete the calculation.

* Although mass flow rates should theoretically be used, engineers often use volumetric flow rates instead during preliminary analysis, since the density of all  airstreams is about the same and the inaccuracy introduced is generally small.

Related Answered Questions