Question 5.7: A city plans a pipeline to transport water from a distant wa...

A city plans a pipeline to transport water from a distant watershed area to the city. The pipeline will cost $8 million and will have an expected life of 70 years. The city expects to keep the water line in service indefinitely. Compute the capitalized cost, assuming 7% interest.