Question 11.1: A public accounting firm estimates that an audit will requir...

A public accounting firm estimates that an audit will require the following work:

Type of Auditor Estimated Hours Cost per Hour Standard Costs
Manager 10 $50 $500
Senior 20 40 800
Staff 40 30 1,200
Total 70 $2,500

The following were the actual hours and costs:

Type of Auditor Actual Hours Actual Cost per Hour  Actual Costs
Manager 9 $52 $468
Senior 22 38 836
Staff 44 30 1,320
Total 75 $2,624

Calculate the direct labor, labor rate, and labor efficiency variances for each type of auditor and interpret them.

The blue check mark means that this solution has been answered and checked by an expert. This guarantees that the final answer is accurate.
Learn more on how we answer questions.

The direct labor variance for each type of auditor follows:

Type of Auditor Actuals Costs Standard Costs Direct labor Variance
Manager $468 $500 ($32)
Senior 836 800 36
Staff 1,320 1,200 120
Totals $2,624 $2,500 $124  Unfavorable
The  labor rate variance for each of auditor follows :
Manager ($52 per hour – $50 per hour×9hours) = $18
Senior ($38 per hour – $40 per hour ×22) = (44)
Staff ($30 per hour – $30 per hour ×44) = 0
Total labor rate variance  $ (26) Favorable
The labor efficiency variance foe each type of auditor is as follows:
Manager (9 hours – 10 hours ×$50 per hour) = ($50)
Senior(22 hours -20 hours× $40 per hour) = 80
Staff (44 hours – 40 hours ×$30 per hour) = 120
Total labor efficiency variance $150  Unfavorable

Note that the direct labor variance equals the sum of the labor rate and labor efficiency variances. The favorable labor rate variance means that, on average, the auditors were paid less than expected, although managers were paid more than expected. The unfavorable labor efficiency variance means that, on average, the auditors took longer to complete the audit than expected. The manager, however, spent less time on the audit than expected.

Related Answered Questions

Question: 11.4

Verified Answer:

Budgeted number of direct labor hours based on bud...
Question: 11.CR.11

Verified Answer:

Satisficing behavior occurs when employees work ha...
Question: 11.CR.12

Verified Answer:

The budgeted usage is based on estimates at the be...
Question: 11.CR.14

Verified Answer:

Overhead standards are intended to motivate manage...
Question: 11.CR.15

Verified Answer:

Variances represent deviations from plans and mana...
Question: 11.CR.17

Verified Answer:

Standard costs are frequently based on past experi...