Question 10.5: Added Benefit versus Reduced Cost in a Bridge Widening Proje...

Added Benefit versus Reduced Cost in a Bridge Widening Project

A project is being considered by the Tennessee Department of Transportation to replace an aging bridge across the Cumberland River on a state highway. The existing two-lane bridge is expensive to maintain and creates a traffic bottleneck because the state highway is four lanes wide on either side of the bridge. The new bridge can be constructed at a cost of $300,000, and estimated annual maintenance costs are $10,000. The existing bridge has annual maintenance costs of $18,500. The annual benefit of the new four-lane bridge to motorists, due to the removal of the traffic bottleneck, has been estimated to be $25,000. Conduct a B–C analysis, using a MARR of 8% and a study period of 25 years, to determine whether the new bridge should be constructed.

The blue check mark means that this solution has been answered and checked by an expert. This guarantees that the final answer is accurate.
Learn more on how we answer questions.

Treating the reduction in annual maintenance costs as a reduced cost:
B–C = $25,000/[$300,000(A/P, 8%, 25) − ($18,500 − $10,000)]
B–C = 1.275 > 1; construct new bridge.
Treating the reduction in annual maintenance costs as an increased benefit:
B–C = [$25,000 + ($18,500 − $10,000)]/[$300,000(A/P, 8%, 25)]
B–C = 1.192 > 1; construct new bridge.
Therefore, the decision to classify a cash-flow item as an additional benefit or as a reduced cost will affect the magnitude of the calculated B–C ratio, but it will have no effect on project acceptability.