Question 23.17: Begin the design of a complete-mix BOD removal and nitrifica...

Begin the design of a complete-mix BOD removal and nitrification stage for Tempe’s new BPR wastewater treatment plant. As a first step determine the SRT and volume of tank required for nitrification using the following design data:

Influent data after primary settling

Design flow rate = 90,000 m³/d
BOD_{5} = 138 mg/L
bCOD = 220 mg/L
rbCOD = 80 mg/L
Total Kjeldahl nitrogen (TKN) = 35 mg/L
NH_{3}-N = 25 mg/L
Soluble phosphorus = 8 g/m³
Total suspended solids (TSS) = 70 mg/L
Volatile suspended solids (VSS) = 60 mg/L
Biodegradable volatile suspended solids = 40 mg/L
Minimum sustained temperature = 20°C
pH = 7.0
Alkalinity = 220 mg/L as CaCO_{3}

Effluent discharge standards

bCOD ≤ 20 mg/L
NH_{3}-N ≤ 1.0 mg/L
NO_{3}-N ≤ 10 mg/L
TSS ≤ 10 mg/L
Total phosphorus ≤ 2.0 mg/L

Assume DO for aeration tank nitrification = 2.0 mg/L; MLSS = 3,000 mg/L, MLVSS = (0.8) MLSS, NO = 80% of TKN, and RAS = 0.60(Q).

The "Step-by-Step Explanation" refers to a detailed and sequential breakdown of the solution or reasoning behind the answer. This comprehensive explanation walks through each step of the answer, offering you clarity and understanding.
Our explanations are based on the best information we have, but they may not always be right or fit every situation.
The blue check mark means that this solution has been answered and checked by an expert. This guarantees that the final answer is accurate.
Learn more on how we answer questions.
Already have an account?

Related Answered Questions

Question: 23.15

Verified Answer:

a. The anoxic fill time must be greater than the t...
Question: 23.14

Verified Answer:

a. The time required for nitrification must be les...
Question: 23.10

Verified Answer:

a. Assume that kinetic coefficients for heterotrop...