Question 23.17: Begin the design of a complete-mix BOD removal and nitrifica...
Begin the design of a complete-mix BOD removal and nitrification stage for Tempe’s new BPR wastewater treatment plant. As a first step determine the SRT and volume of tank required for nitrification using the following design data:
Influent data after primary settling
Design flow rate = 90,000 m³/d
BOD_{5} = 138 mg/L
bCOD = 220 mg/L
rbCOD = 80 mg/L
Total Kjeldahl nitrogen (TKN) = 35 mg/L
NH_{3}-N = 25 mg/L
Soluble phosphorus = 8 g/m³
Total suspended solids (TSS) = 70 mg/L
Volatile suspended solids (VSS) = 60 mg/L
Biodegradable volatile suspended solids = 40 mg/L
Minimum sustained temperature = 20°C
pH = 7.0
Alkalinity = 220 mg/L as CaCO_{3}
Effluent discharge standards
bCOD ≤ 20 mg/L
NH_{3}-N ≤ 1.0 mg/L
NO_{3}-N ≤ 10 mg/L
TSS ≤ 10 mg/L
Total phosphorus ≤ 2.0 mg/L
Assume DO for aeration tank nitrification = 2.0 mg/L; MLSS = 3,000 mg/L, MLVSS = (0.8) MLSS, NO = 80% of TKN, and RAS = 0.60(Q).