Question 5.A.17: Calculate the standard deviation for the Satellite project. ...

Calculate the standard deviation for the Satellite project. Which project has the higher level of risk?

The blue check mark means that this solution has been answered and checked by an expert. This guarantees that the final answer is accurate.
Learn more on how we answer questions.

To answer this activity, the steps outlined above must be followed. Thus:

Step 1. Calculate the ENPV:

(a)
NPV
£m
(b)
Probability of occurrence
(a × b)
ENPV
£m
15 0.6 9.0
20 0.2 4.0
40 0.2 8.0
21.0

Step 2. Calculate the deviations around the ENPV:

(a)
Possible NPV
£m
(b)
ENPV
£m
(a – b)
Deviation
£m
15 21 -6
20 21 -1
40 21 19

Step 3. Calculate the variance (that is, sum the squared deviations):

Deviations
£m
Squared deviations
£m
-6 36
-1 1
19 361
                                                                                 Variance        398

Step 4. Find the square root of the variance (that is, the standard deviation):*

Standard deviation = \sqrt{398(£m)^{2}}

= £19.95m

The Satellite project has the higher standard deviation and therefore the greater variability of possible outcomes. Hence, it has the higher level of risk.

* Computer software or calculators with statistical functions can be used to calculate the standard deviation and so this manual approach need not be used in practice. It is shown here for illustrative purposes.

Related Answered Questions

Question: 5.A.18

Verified Answer:

We can see from our earlier calculations that the ...
Question: 5.A.20

Verified Answer:

The answer is no. Even if two projects could be fo...