Holooly Plus Logo

Question 25.2: MRP Time-Phased Quantity Requirements To illustrate these va...

MRP Time-Phased Quantity Requirements
To illustrate these various complicating factors, consider the MRP procedure for component C4, which is used in product P1. This part also happens to be used on product P2 of the master schedule in Figure 25.2. The product structure for P2 is shown in Figure 25.6. Component C4 is made out of material M4, one unit of M4 for each unit of C4, and the inventory status of M4 is given in Figure 25.5. The lead times and inventory status for each of the other items needed in the MRP calculations are shown in the table below. Complete the MRP calculations to determine the time-phased requirements for items S2, S3, C4, and M4, based on the requirements for P1 and P2 given in the MPS of Figure 25.2. It is assumed that the inventory on hand or on order for P1, P2, S2, S3, and C4 is zero for all future periods except for the calculated values in this problem solution.

Item lead Time Inventory
P1 Assembly lead time = 1 week No inventory on hand or on order
P2 Assembly lead time = 1 week No inventory on hand or on order
S2 Assembly lead time = 1 week No inventory on hand or on order
S3 Assembly lead time = 1 week No inventory on hand or on order
C4 Manufacturing lead time = 2 weeks No inventory on hand or on order
M4 Ordering lead time = 3 weeks See Figure 25.5.

 

1653856945731
1653858000746
The "Step-by-Step Explanation" refers to a detailed and sequential breakdown of the solution or reasoning behind the answer. This comprehensive explanation walks through each step of the answer, offering you clarity and understanding.
Our explanations are based on the best information we have, but they may not always be right or fit every situation.
The blue check mark means that this solution has been answered and checked by an expert. This guarantees that the final answer is accurate.
Learn more on how we answer questions.
Already have an account?

Related Answered Questions