Question 25.2: MRP Time-Phased Quantity Requirements To illustrate these va...
MRP Time-Phased Quantity Requirements
To illustrate these various complicating factors, consider the MRP procedure for component C4, which is used in product P1. This part also happens to be used on product P2 of the master schedule in Figure 25.2. The product structure for P2 is shown in Figure 25.6. Component C4 is made out of material M4, one unit of M4 for each unit of C4, and the inventory status of M4 is given in Figure 25.5. The lead times and inventory status for each of the other items needed in the MRP calculations are shown in the table below. Complete the MRP calculations to determine the time-phased requirements for items S2, S3, C4, and M4, based on the requirements for P1 and P2 given in the MPS of Figure 25.2. It is assumed that the inventory on hand or on order for P1, P2, S2, S3, and C4 is zero for all future periods except for the calculated values in this problem solution.
Item | lead Time | Inventory |
P1 | Assembly lead time = 1 week | No inventory on hand or on order |
P2 | Assembly lead time = 1 week | No inventory on hand or on order |
S2 | Assembly lead time = 1 week | No inventory on hand or on order |
S3 | Assembly lead time = 1 week | No inventory on hand or on order |
C4 | Manufacturing lead time = 2 weeks | No inventory on hand or on order |
M4 | Ordering lead time = 3 weeks | See Figure 25.5. |
Our explanations are based on the best information we have, but they may not always be right or fit every situation.
Learn more on how we answer questions.