Question 3.6: Power-Sizing Model for Cost Estimating Suppose that an aircr...

Power-Sizing Model for Cost Estimating

Suppose that an aircraft manufacturer desires to make a preliminary estimate of the cost of building a 600-MW fossil-fuel plant for the assembly of its new long distance aircraft. It is known that a 200-MW plant cost $100 million 20 years ago when the approximate cost index was 400, and that cost index is now 1,200. The cost-capacity factor for a fossil-fuel power plant is 0.79.

The blue check mark means that this solution has been answered and checked by an expert. This guarantees that the final answer is accurate.
Learn more on how we answer questions.

Before using the power-sizing model to estimate the cost of the 600-MW plant (C_{A}), we must first use the cost index information to update the known cost of the 200-MW plant 20 years ago to a current cost. Using Equation (3-1 : C_{n}= C_{k} \left(\frac {\bar { I_{n}} }{\bar{I_{k}} } \right) ), we find that the current cost of a 200-MW plant is

C_{B}= $100 million \left( \frac{ 12.000}{400} \right) = $300 million.

So, using Equation (3-4 : C_{A}= C_{B} \left( \frac { S_{A}}{S_{B}} \right)^{X}), we obtain the following estimate for the 600-MW plant:

C_{A} = $300 million \left(\frac{600-MW}{200-MW} \right)^{0.79}

C_{A}= $300 million × 2.38 = $714 million.

Related Answered Questions

Question: 3.9

Verified Answer: