Question 17.p.1: The following table contains information related to the majo...

The following table contains information related to the major activities of a research project. Use the information to do the following:
a. Draw a precedence diagram using AOA.
b. Find the critical path.
c. Determine the expected length of the project.

Activity Immediate
Predecessor
Expected
Time (days)
a 5
c a 8
d c 2
b a 7
e 3
f e 6
i b.d 10
m f,i 8
g 1
h g 2
k h 17
end k,m
The blue check mark means that this solution has been answered and checked by an expert. This guarantees that the final answer is accurate.
Learn more on how we answer questions.

a. In constructing networks, these observations can be useful.
(1) Activities with no predecessors are at the beginning (left side) of the network.
(2) Activities with multiple predecessors are located at path intersections.
Complete the diagram in sections. Go down the activity list in order to avoid overlooking any activities.

AOA diagram

AON diagram

Here are some additional hints for constructing a precedence diagram.
(1) Use pencil.
(2) Start and end with a single node.
(3) Avoid having paths cross each other.
(4) Have activities go from left to right.
(5) Use only one arrow between any pair of nodes.
b. and c.

Path Length (days)
a–c–d–i–m* 5 + 8 + 2 + 10 + 8 = 33†
a–b–i–m 5 + 7 + 10 + 8 = 30
e–f–m 3 + 6 + 8 = 17
g–h–k 1 + 2 + 17 = 20

*Critical path
†Expected project duration

2
3

Related Answered Questions

Question: 17.p.3

Verified Answer:

Standard deviations cannot be added, but variances...
Question: 17.4

Verified Answer:

Either the starting times or the finishing times c...