Question 9.2: The job-order cost sheet for a special product is as follows...

The job-order cost sheet for a special product is as follows:

job number:711
Date started: 05/06
Date completed:06/15
Raw                Materials Direct       Labor
Date Type Cost Qty. Amount rate Hours Amount
26-May 130 £30 6 £180 £18 5 £90
15-Jun 248 10 20 200 15 10 150
£380 15 £240
Total direct materials                              £380
Total direct labor 99
Overhead(5 direct labor hours @£10/hours) 150
Total job cost 770

Overhead is allocated based on direct labor hours (DLH). The parts were in the Raw Materials inventory before being used on Job 711. The product is sold on July 10. Identify the cost flows on May 26, June 15, and July 10.

The blue check mark means that this solution has been answered and checked by an expert. This guarantees that the final answer is accurate.
Learn more on how we answer questions.

Cost flows:

On 05/26:    €180 from Raw Materials inventory to Work-in-Process
€90 from Labor to Work-in-Process
€50 from Overhead to Work-in-Process for overhead related to direct labor hours (5 DLH × €10/DLH)
On 06/15: €200 from Raw Materials inventory to Work-in-Process
€150 from Labor to Work-in-Process
€100 from Overhead to Work-in-Process for overhead related to direct labor hours (10 DLH × €10/DLH)
When finished: €770 from Work-in-Process to Finished Goods
On 07/10: €770 from Finished Goods to Cost of Goods Sold

Related Answered Questions

Question: 9.5

Verified Answer:

The activities are summarized as follows: Chan...
Question: 9.4

Verified Answer:

The manufacture estimates the following overhead c...
Question: 9.CR.12

Verified Answer:

By allocating costs first to departments, the mana...
Question: 9.CR.13

Verified Answer:

The primary purpose of process costing is to ident...
Question: 9.CR.14

Verified Answer:

Equivalent unit calculation is used when partially...