Question : (a) Estimate the value of the ENR construction cost index by...

(a) Estimate the value of the ENR construction cost index by using the average (compounded) percentage change in its value between 1995 and 2005 to predict the value in 2009.

(b) How much difference (numerical) is there between the estimated and actual 2009 values? Is this an underestimate or overestimate?

The Blue Check Mark means that this solution has been answered and checked by an expert. This guarantees that the final answer is accurate.
Learn more on how we answer questions.

(a) First find the compounded percentage increase p between 1995 and 2005.

 

7446 = 5471 (F/P,p,10)

 

1.36099 = { (1+p) }^{ 10 }

 

\quad p = 0.0313 or 3.13 % per year

 

Predicted index value in 2009 = 7446(F/P,3.13%,4)

 

\quad \quad \quad\quad \quad \quad \quad \quad \quad \quad \quad \quad = 7446{ (1+0.0313) }^{ 4 }

 

\quad \quad \quad \quad \quad \quad \quad \quad \quad \quad \quad\quad = 8423

 

(b) Difference = 8570 – 8423

 

\quad \quad \quad \quad\quad  = 147 (underestimate)