Holooly Plus Logo

Question 13.8: A Conceptual Real-Options Decision Framework When You Can Re...

A Conceptual Real-Options Decision Framework When You Can Resolve Uncertainty by Waiting

Consider a project that requires a $200 million investment and expects to last three years with the following cash flows:

Annual Cash Flow Probability Demand
$250 million 0.25 Good
$100 million 0.30 Moderate
$ 35 million 0.45 Poor

The cost of capital that accounts for the market risk, known as the risk-adjusted discount rate, is 10%, and a risk-free interest rate is known to be 6%. Can we defer the project by one year and then implement it only if demand is either moderate or good?

The "Step-by-Step Explanation" refers to a detailed and sequential breakdown of the solution or reasoning behind the answer. This comprehensive explanation walks through each step of the answer, offering you clarity and understanding.
Our explanations are based on the best information we have, but they may not always be right or fit every situation.
The Blue Check Mark means that this solution has been answered and checked by an expert. This guarantees that the final answer is accurate.
Learn more on how we answer questions.

Related Answered Questions