A product design engineer must decide if a redundant component is cost-justified is a certain system. The system in question has a critical component with a probability of .98 of operating . failure would involve a cost of $ 20.000. For a cost of $ 100 , aswitch could be added that would automatically transfer the system to the backup component in the event of a failure . Should the backup be added if the backup probability is also. 98?