Holooly Plus Logo

Question 4.DI.2: Apply ABC to Manufacturer Casey Company has five activity co...

Apply ABC to Manufacturer

Casey Company has five activity cost pools and two products. It estimates production of 200,000 units of its automobile scissors jack and 80,000 units of its truck hydraulic jack. Having identified its activity cost pools and the cost drivers for each cost pool, Casey Company accumulated the following data relative to those activity cost pools and cost drivers.

Annual Overhead Data Estimated Use of Cost Drivers per Product
Activity Cost Pools Cost Drivers Estimated Overhead Estimated Use of Cost Drivers per Activity Scissors Jacks Hydraulic Jacks
Ordering and receiving Purchase orders $200,000 2,500 orders 1,000 1,500
Machine setup Setups 600,000 1,200 setups 500 700
Machining Machine hours 2,000,000 800,000 hours 300,000 500,000
Assembling Parts 1,800,000 3,000,000 parts 1,800,000 1,200,000
Inspecting and testing Tests 700,000 35,000 tests 20,000 15,000
$5,300,000

Using the above data, do the following.
a. Prepare a schedule showing the computations of the activity-based overhead rates per cost driver.
b. Prepare a schedule assigning each activity’s overhead cost to the two products.
c. Compute the overhead cost per unit for each product.
d. Comment on the comparative overhead cost per unit.

The "Step-by-Step Explanation" refers to a detailed and sequential breakdown of the solution or reasoning behind the answer. This comprehensive explanation walks through each step of the answer, offering you clarity and understanding.
Our explanations are based on the best information we have, but they may not always be right or fit every situation.
The Blue Check Mark means that this solution has been answered and checked by an expert. This guarantees that the final answer is accurate.
Learn more on how we answer questions.

Related Answered Questions