Question 10.st.7: Barney plc manufactures deluxe cat baskets in batches of 300...

Barney plc manufactures deluxe cat baskets in batches of 300. During April, Batch
no. 567 took 20 hours to machine. Sixty cat baskets failed to pass an inspection, but
of these, 40 were thought to be rectifiable. The remaining 20 were scrapped, and the
scrap value was credited to the cost of the batch as a whole. Rectification work took
nine hours. Costs were as follows:

Batch no. 567 £
Raw materials per cat basket 1.60
Scrap value per cat basket 0.86
Machinists’ hourly rate 4.20
Machine-hour overhead 3.60
Setting up of machine – normal machining 21.00
Setting up of machine – rectification 18.00

Calculate:
(a) The cost of a full batch, in total and per unit, if all units pass inspection.
(b) The actual cost of Batch no. 567, in total and per unit, after crediting the recovery
value of the scrapped items, and including the rectification costs.
(c) The loss incurred because of defective work.

The "Step-by-Step Explanation" refers to a detailed and sequential breakdown of the solution or reasoning behind the answer. This comprehensive explanation walks through each step of the answer, offering you clarity and understanding.
Our explanations are based on the best information we have, but they may not always be right or fit every situation.
The Blue Check Mark means that this solution has been answered and checked by an expert. This guarantees that the final answer is accurate.
Learn more on how we answer questions.

Related Answered Questions