Capacity requirements planning Given the following production schedule in units and the production standards for labor and machine for this product, determine the labor and machine capacity requirements for each week. Then compute the percent utilization of labor and machines in each week if labor is 200 hours per week and machine capacity is 250 hours per week.

Production Schedule:
Week 1 2 3 4
Quantity 200 300 100 150
Standard Times:
Labor .5 hour/unit
Machine 1·0  hour/unit
The "Step-by-Step Explanation" refers to a detailed and sequential breakdown of the solution or reasoning behind the answer. This comprehensive explanation walks through each step of the answer, offering you clarity and understanding.
Our explanations are based on the best information we have, but they may not always be right or fit every situation.
The Blue Check Mark means that this solution has been answered and checked by an expert. This guarantees that the final answer is accurate.
Learn more on how we answer questions.

Related Answered Questions