Capacity requirements planning Given the following production schedule in units and the production standards for labor and machine for this product, determine the labor and machine capacity requirements for each week. Then compute the percent utilization of labor and machines in each week if labor is 200 hours per week and machine capacity is 250 hours per week.
Production Schedule: | ||||
Week | 1 | 2 | 3 | 4 |
Quantity | 200 | 300 | 100 | 150 |
Standard Times: | ||||
Labor | .5 hour/unit | |||
Machine | 1·0 hour/unit |