Holooly Plus Logo

Question 10.5: Project Cash Flows for a Cost-Only Project. Alcoa Aluminum’s...

Project Cash Flows for a Cost-Only Project

Alcoa Aluminum’s McCook plant produces aluminum coils, sheets, and plates. Its annual production runs at 400 million pounds. In an effort to improve McCook’s current production system, an engineering team led by the divisional vice president went on a fact-finding tour of Japanese aluminum and steel companies to observe their production systems and methods. Cited among the team’s observations were large fans, which the Japanese companies used to reduce the time that coils need to cool down after various processing operations. Cooling the hot process coils with the fans was estimated to significantly reduce the queue or work-in-process (WIP) inventory buildup allowed for cooling. The approach also reduced production lead-time and improved delivery performance. The possibility of reducing production time and, as a consequence, the WIP inventory, excited the team members, particularly the vice president. After the trip, Neal Donaldson, the plant engineer, was asked to investigate the economic feasibility of installing cooling fans at the McCook plant. Neal’s job was to justify the purchase of cooling fans for his plant. He was given one week to prove that the idea was a good one. Essentially, all he knew was the number of fans, their locations, and the project cost. Everything else was left to Neal’s devices. Suppose that he compiled the following financial data.

  • The project will require an investment of $536,000 in cooling fans now.
  • The cooling fans would provide 16 years of service with no appreciable salvage values, considering the removal costs.
  • It is expected that the amount of time required between hot rolling and the next operation would be reduced from five days to two days. Cold-rolling queue time also would be reduced from two days to one day for each cold-roll pass. The net effect of these changes would be a reduction in the WIP inventory at a value of $2,121,000. Because of the lead-time involved in installing the fans, as well as the consumption of stockpiled WIP inventory, this working-capital release would be realized one year after the fans are installed.
  • The cooling fans will be depreciated according to seven-year MACRS.
  • Annual electricity costs are estimated to rise by $86,000.
  • The firm’s after-tax required rate of return is known to be 20% for this type of cost-reduction project.

Develop the project cash flows over the service period of the fans, and determine whether the investment is a wise one, based on 20% interest and 40% marginal tax rate.

The "Step-by-Step Explanation" refers to a detailed and sequential breakdown of the solution or reasoning behind the answer. This comprehensive explanation walks through each step of the answer, offering you clarity and understanding.
Our explanations are based on the best information we have, but they may not always be right or fit every situation.
The Blue Check Mark means that this solution has been answered and checked by an expert. This guarantees that the final answer is accurate.
Learn more on how we answer questions.

Related Answered Questions