Provide a simple payback period analysis for implementing a cogeneration system to be installed in a hospital. Use the following characteristics for the cogeneration system:
• Fuel input rate: 10,000 Btu/kWh
• Heat recovery rate: 5,500 Btu/kWh
• Maintenance cost: $0.02/ kWh
• Maximum electrical output: 200 kW or 300 kW
• Installed equipment cost: $1000/kW
Table 13.10 summarizes the energy usage and cost of the hospital. Assume that the boiler(s) efficiency is 70 percent. For this analysis, assume also that the cogeneration system requires diesel fuel only (the other option is dual fuel). Assume the heating value of diesel fuel is 140,000 Btu/ gal.
TABLE 13.10 Monthly Utility Data for the Hospital Used in Example 13.3
Utility Summary | |||||
Fuel Oil | Electricity | ||||
($) | (Gallon) | ($) | (kW) | (kWh) | Month |
14,911 | 20,659 | 2,7020 | 546 | 226,400 | January |
12,639 | 20,555 | 28,949 | 572 | 273,600 | February |
9,670 | 16,713 | 31,048 | 564 | 280,800 | March |
4,742 | 10,235 | 25,251 | 526 | 228,000 | April |
5,347 | 12,193 | 28,755 | 692 | 246,000 | May |
9,001 | 12,352 | 36,604 | 884 | 301,200 | June |
3,122 | 20,604 | 45,031 | 1,040 | 346,800 | July |
5,711 | 17,276 | 46,374 | 944 | 403,200 | August |
3,762 | 10,457 | 36,541 | 860 | 303,600 | September |
3,726 | 10,890 | 33,559 | 872 | 276,000 | October |
5,255 | 13,478 | 28,042 | 662 | 272,400 | November |
7,808 | 17,661 | 25,041 | 524 | 276,000 | December |
85,694 | 183,073 | 393,215 | 3,434,000 | Total |