The preliminary work sample of an operation indicates the following:

Number of times operator working 60
Number of times operator idle 40
Total number of preliminary observations 100

What is the required sample size for a 99.73% confidence level with ±4, precision?

The Blue Check Mark means that this solution has been answered and checked by an expert. This guarantees that the final answer is accurate.
Learn more on how we answer questions.

z = 3 for 99.73 confidence; p = \frac{60}{100} = 0.6; h = 0.04

So:
n = \frac{z^2 p(1 – p)}{h^2} = \frac{(3)^2 (0.6)(0.4)}{(0.04)^2} = 1,350 sample size