Question 10.SP.3: The preliminary work sample of an operation indicates the fo...

The preliminary work sample of an operation indicates the following:

Number of times operator working 60
Number of times operator idle 40
Total number of preliminary observations 100

What is the required sample size for a 99.73% confidence level with ±4, precision?