Question 16.SP.4: S/O rule. Using the following information, determine an orde...

S/O rule. Using the following information, determine an order processing sequence using the S/O priority rule.

Order Processing
Time
Remaining
(days)
Due Date
(days)
Number of
Operations
Remaining
A 20 30 2
B 11 18 5
C 10 6 2
D 16 23 4
The blue check mark means that this solution has been answered and checked by an expert. This guarantees that the final answer is accurate.
Learn more on how we answer questions.

Assume times are independent of processing sequence.

Order (1)
Remaining
Processing
Time
(2)

Due Date

(3)

(2) − (1)
Slack

(4)

Number of
Operations

(5)

Ratio

(6)

Rank
(sequence)

A 20 30 10 2 5.00 4
B 11 18 7 5 1.40 2
C 10 6 −4 2 −2.00 1
D 16 23 7 4 1.75 3

(Note that one ratio is negative. When negatives occur, assign the lowest rank to the most negative number.)