Question 17.5: Computing Expected Activity Times and Variances, and the Exp...

Computing Expected Activity Times and Variances, and the Expected Duration and Standard Deviation of Each Path

The network diagram for a project is shown in the accompanying figure, with three time estimates for each activity. Activity times are in weeks. Do the following:

a. Compute the expected time for each activity and the expected duration for each path.

b. Identify the critical path.

c. Compute the variance of each activity and the variance and standard deviation of each path.

17.5
The blue check mark means that this solution has been answered and checked by an expert. This guarantees that the final answer is accurate.
Learn more on how we answer questions.

a.

Path Activity TIMES te = \frac{t_{o}  +  4t_{m}  +  t_{p}}{6} Path Total
to tm tp
a–b–c a 1 3 4  

\left. \begin{matrix} 2.83\\ \\4.00 \\\\3.17 \end{matrix} \right\}

 

 

10.00

b 2 4 6
c 2 3 5
d–e–f d 3 4 5  

\left. \begin{matrix} 4.00\\ \\5.00\\ \\7.00 \end{matrix} \right\}

 

 

16.00

e 3 5 7
f 5 7 9
g–h–i g 2 3 6  

\left. \begin{matrix} 3.33\\ \\6.00\\ \\4.17 \end{matrix} \right\}

 

 

13.50

h 4 6 8
i 3 4 6

b. The path that has the longest expected duration is the critical path. Because path d–e–f has the largest path total, it is the critical path.

c.

Path Activity TIMES \sigma^{2}  _{act}= \frac{\left(t_{p}  –  t_{o}\right)^{2}}{36} \sigma^{2}  _{path} \sigma_{path}
to tm tp
a–b–c a 1 3 4 \left. \begin{matrix}(4 − 1)^{2}/36 = 9/36 \\ \\ (6 − 2)^{2}/36 = 16/36\\ \\ (5 − 2)^{2}/36 = 9/36 \end{matrix} \right\}  

34/36 5 0.944

 

0.97

b 2 4 6
c 2 3 5
d–e–f d 3 4 5 \left. \begin{matrix}(5 − 3)^{2}/36 = 4/36\\ \\ (7 − 3)^{2}/36 = 16/36\\ \\ (9 − 5)^{2}/36 = 16/36\end{matrix} \right\}  

36/36 5 1.00

 

1.00

e 3 5 7
f 5 7 9
g–h–i g 2 3 6 \left. \begin{matrix}(6 − 2)^{2}/36 = 16/36\\ \\ (8 − 4)^{2}/36 = 16/36\\ \\ (6 − 3)^{2}/36 = 9/36\end{matrix} \right\}  

41/36 5 1.139

 

1.07

h 4 6 8
i 3 4 6

Related Answered Questions

Question: 17.SP.3

Verified Answer:

Standard deviations cannot be added, but variances...
Question: 17.4

Verified Answer:

Either the starting times or the finishing times c...