An assembly operation has a 90 percent learning curve. The line has just begun work on a new item; the initial unit required 28 hours. Estimate the time that will be needed to complete:

a. The first five units.
b. Units 20 through 25.

Step-by-Step
The 'Blue Check Mark' means that this solution was answered by an expert.
Learn more on how do we answer questions.

Use the total time factor in the 90 percent column of Table 7S.1 .

a. Table value: 4.339.
Estimated time for five units: 28(4.339) = 121.49 hours.

b. The total time for units 20 through 25 can be determined by subtraction:

TABLE 7S.1 Learning curve coefficients

70% 75% 80% 85% 90%
Unit
Number
Unit
Time
Total
Time
Unit
Time
Total
Time
Unit
Time
Total
Time
Unit
Time
Total
Time
Unit
Time
Total
Time
1 1.000 1.000 1.000 1.000 1.000 1.000 1.000 1.000 1.000 1.000
2 .700 1.700 .750 1.750 .800 1.800 .850 1.850 .900 1.900
3 .568 2.268 .634 2.384 .702 2.502 .773 2.623 .846 2.746
4 .490 2.758 .562 2.946 .640 3.142 .723 3.345 .810 3.556
5 .437 3.195 .513 3.459 .596 3.738 .686 4.031 .783 4.339
6 .398 3.593 .475 3.934 .561 4.299 .657 4.688 .762 5.101
7 .367 3.960 .446 4.380 .534 4.834 .634 5.322 .744 5.845
8 .343 4.303 .422 4.802 .512 5.346 .614 5.936 .729 6.574
9 .323 4.626 .402 5.204 .493 5.839 .597 6.533 .716 7.290
10 .306 4.932 .385 5.589 .477 6.315 .583 7.116 .705 7.994
11 .291 5.223 .370 5.958 .462 6.777 .570 7.686 .695 8.689
12 .278 5.501 .357 6.315 .449 7.227 .558 8.244 .685 9.374
13 .267 5.769 .345 6.660 .438 7.665 .548 8.792 .677 10.052
14 .257 6.026 .334 6.994 .428 8.092 .539 9.331 .670 10.721
15 .248 6.274 .325 7.319 .418 8.511 .530 9.861 .663 11.384
16 .240 6.514 .316 7.635 .410 8.920 .522 10.383 .656 12.040
17 .233 6.747 .309 7.944 .402 9.322 .515 10.898 .650 12.690
18 .226 6.973 .301 8.245 .394 9.716 .508 11.405 .644 13.334
19 .220 7.192 .295 8.540 .388 10.104 .501 11.907 .639 13.974
20 .214 7.407 .288 8.828 .381 10.485 .495 12.402 .634 14.608
21 .209 7.615 .283 9.111 .375 10.860 .490 12.892 .630 15.237
22 .204 7.819 .277 9.388 .370 11.230 .484 13.376 .625 15.862
23 .199 8.018 .272 9.660 .364 11.594 .479 13.856 .621 16.483
24 .195 8.213 .267 9.928 .359 11.954 .475 14.331 .617 17.100
25 .191 8.404 .263 10.191 .355 12.309 .470 14.801 .613 17.713
26 .187 8.591 .259 10.449 .350 12.659 .466 15.267 .609 18.323
27 .183 8.774 .255 10.704 .346 13.005 .462 15.728 .606 18.929
28 .180 8.954 .251 10.955 .342 13.347 .458 16.186 .603 19.531
29 .177 9.131 .247 11.202 .338 13.685 .454 16.640 .599 20.131
30 .174 9.305 .244 11.446 .335 14.020 .450 17.091 .596 20.727

 

Hours
Total time for 25 units: 28(17.713) = 495.96
\underline{\text{–Total time for 19 units:}\ \ \ \ \ \ } 28(13.974) = 391.27
Total time for units 20 through 25 104.69