Question 17.SP.5: Costs for a project are $12,000 per week for as long as the ...

Costs for a project are $12,000 per week for as long as the project lasts. The project manager has supplied the cost and time information shown. Use the information to:

a. Determine an optimum crashing plan

b. Graph the total costs for the plan

Activity Crashing
Potential
(weeks)
Cost per Week to
Crash
a 3 $11,000
b 3   3,000 first week,
$ 4,000 others
c 2    6,000
d 1    1,000
e 3    6,000
f 1    2,000
17.SP.5 1
The blue check mark means that this solution has been answered and checked by an expert. This guarantees that the final answer is accurate.
Learn more on how we answer questions.

a. (1) Compute path lengths and identify the critical path:

Path Duration (weeks)
a–b 24 (critical path)
c–d 19
e–f 23

(2) Rank critical activities according to crash costs:

Activity Cost per Week to Crash
b $ 3,000
a 11,000

Activity b should be shortened one week since it has the lower crashing cost. This would reduce indirect costs by $12,000 at a cost of $3,000, for a net savings of $9,000. At this point, paths a–b and e–f would both have a length of 23 weeks, so both would be critical.

(3) Rank activities by crashing costs on the two critical paths:

Path Activity Cost per Week to Crash
a–b b $ 4,000
a 11,000
e–f f    2,000
e    6,000

Choose one activity (the least costly) on each path to crash: b on a–b and f on e–f, for a total cost of $4,000 + $2,000 = $6,000 and a net savings of $12,000 − $6,000 = $6,000.

(4) Check to see which path(s) might be critical: a–b and e–f would be 22 weeks in length, and c–d would still be 19 weeks.

(5) Rank activities on the critical paths:

Path Activity Cost per Week to Crash
a–b b $ 4,000
a 11,000
e–f e 6,000
f (no further crashing possible)

Crash b on path a–b and e on e–f for a cost of $4,000 + $6,000 = $10,000, for a net savings of $12,000 − $10,000 = $2,000.

(6) At this point, no further improvement is possible: paths a–b and e–f would be 21 weeks in length, and one activity from each path would have to be shortened. This would mean activity a at $11,000 and e at $6,000 for a total of $17,000, which exceeds the $12,000 potential savings in costs.

b. The following table summarizes the results, showing the length of the project after crashing n weeks:

Path n = 0 1 2 3
a–b 24 23 22 21
c–d 19 19 19 19
e–f 23 23 22 21
Activity crashed b b,f b,e
Crashing costs ($000) 3 6 10

A summary of costs for the preceding schedule would look like this:

Project
Length
Cumulative
Weeks
Shortened
Cumulative
Crashing
Costs ($000)
Indirect
Costs ($000)
Total
Costs ($000)
24 0 0 24(12) = 288 288
23 1 3 23(12) = 276 279
22 2 3 + 6 = 9 22(12) = 264 273
21 3 9 + 10 = 19 21(12) = 252 271
20 4 19 + 17 = 36 20(12) = 240 276

The graph of total costs is as follows:

17.SP.5 2

Related Answered Questions

Question: 17.SP.3

Verified Answer:

Standard deviations cannot be added, but variances...
Question: 17.4

Verified Answer:

Either the starting times or the finishing times c...