Question 16.SP.6: For Solved Problem 5, determine what effect splitting jobs c...

For Solved Problem 5, determine what effect splitting jobs c, d, e, and b in work center A would have on the idle time of work center B and on the throughput time. Assume that each job can be split into two equal parts.

The blue check mark means that this solution has been answered and checked by an expert. This guarantees that the final answer is accurate.
Learn more on how we answer questions.

We assume that the processing sequence remains unchanged and proceed on that basis. The solution from the previous problem is shown in the following chart. The next chart shows reduced idle time at center B when splitting is used.

An inspection of these two figures reveals that throughput time has decreased from 20.30 hours to 19.55 hours. In addition, the original idle time was 5.6 hours. After splitting certain jobs, it was reduced to 4.85 hours, so some improvement was achieved. Note that processing times at B are generally less than at A for jobs toward the end of the sequence. As a result, jobs such as e and b at B were scheduled so that they were centered around the finishing times of e and b, respectively, at A, to avoid having to break the jobs due to waiting for the remainder of the split job from A. Thus, the greatest advantage from job splitting generally comes from splitting earlier jobs when Johnson’s rule is used for sequencing.