A 6 ft diameter, 2000 ft long sewer drain pipe is to be installed 24 ft below the ground surface as shown in Figure 8.6. To build this pipe, a long trench must be excavated below the groundwater table as shown. Steel sheet piles (heavy, corrugated sheets of steel) will be installed to keep the sides from collapsing, and the trench will be dewatered with pumps. After the pipeline is installed, the pumps will be removed, the trench will be backfilled, and the sheet piles will be removed.
The dewatering pumps will be placed at 100 ft intervals along the trench. Assuming the sheet piles are perfectly watertight (probably not a good assumption!), draw a flow net and compute the Q for each pump.