Question 10.SP.2: A work operation consisting of three elements has been subje...

A work operation consisting of three elements has been subjected to a stopwatch time study. The recorded observations are shown in the following table. By union contract, the allowance time for the operation is personal time 5%, delay 5%, and fatigue 10%. Determine the standard time for the work operation.

JOB
ELEMENT
OBSERVATIONS (MINUTES) PERFORMANCE
RATING (%)
1 2 3 4 5 6
A .1 .3 .2 .9 .2 .1 90
B .8 .6 .8 .5 3.2 .7 110
C .5 .5 .4 .5 .6 .5 80
The Blue Check Mark means that this solution has been answered and checked by an expert. This guarantees that the final answer is accurate.
Learn more on how we answer questions.

First, delete the two observations that appear to be very unusual (.9 minute for job element A and 3.2 minutes for job element B). Then:

A’s average observed time = \frac{.1 + .3 + .2 + .2 + .1}{5} = 0.18 min
B’s average observed time = \frac{.8 + .6 + .8 + .5 + .7}{5} = 0.68 min
C’s average observed time = \frac{.5 + .5 + .4 + .5 + .6 + .5}{6} = 0.50 min

A’s normal time = (0.18)(0.90) = 0.16 min
B’s normal time = (0.68)(1.10) = 0.75 min
C’s normal time = (0.50)(0.80) = 0.40 min
Normal time for job = 0.16 + 0.75 + 0.40 = 1.31 min
Note, the total allowance factor = 0.05 + 0.05 + 0.10 = 0.20

Then: Standard time = \frac{1.31}{1 – 0.20} = 1.64 min

Related Answered Questions