Question 15.27: It is required to construct a pile foundation comprised of 2...

It is required to construct a pile foundation comprised of 20 piles arranged in 5 columns at distances of 90 cm center to center. The diameter and lengths of the piles are 30 cm and 9 m respectively. The bottom of the pile cap is located at a depth of 2.0 m from the ground surface. The details of the soil properties etc. are as given below with reference to ground level as the datum. The water table was found at a depth of 4 m from ground level.

Drpth (m) Soil properties
From To
0 2 Silt, saturated, \gamma=16 kN / m ^{3}
2 4 Clay, saturated, \gamma=19.2 kN / m ^{3}
4 12 Clay, saturated, \gamma=19.2 kN / m ^{3}, q_{u}=120 kN / m ^{2}, e_{0}=0.80, C_{c}=0.23
12 14 Clay, \gamma=18.24 kN / m ^{3}, q_{u}=90 kN / m ^{2}, e_{0}=1.08, C_{c}=0.34.
14 17 Clay \gamma=20 kN / m ^{3}, q_{u}=180 kN / m ^{2}, e_{0}=0.70, C_{c}=0.2
17 Rocky stratum

Compute the consolidation settlement of the pile foundation if the total load imposed on the foundation is 2500 kN.

The Blue Check Mark means that this solution has been answered and checked by an expert. This guarantees that the final answer is accurate.
Learn more on how we answer questions.

Assume that the total load 2500 kN acts at a depth (2/3 )L = (2/3) x 9 = 6 m from the bottom of the pile cap on a fictitious footing as shown in Fig. 15. 31 (a). This fictitious footing is now at a depth of 8 m below ground level. The size of the footing is 3.9 x 3.0 m. Now three layers are assumed to contribute to the settlement of the foundation. They are: Layer 1 — from 8m to 12m (= 4m thick) below ground level; Layer 2 — from 12mtol4m = 2m thick; Layer 3 — from 14 m to 17 m = 3 m thick. The increase in pressure due to the load on the fictitious footing at the centers of each layer is computed on the assumption that the load is spread at an angle of 2 vertical to 1 horizontal [Fig. 15.31(a)] starting from the edges of the fictitious footing. The settlement is computed by making use of the equation

 

S_{t}=H_{i} \frac{C_{c}}{1+e_{o}} \log \frac{p_{o}+\Delta p}{p_{o}}

 

where p_{o}= the effective overburden pressure at the middle of each layer,

\Delta p= the increase in pressure at the middle of each layer

 

Computation of p_{o}

For Layer 1, p_{o}=2 \times 16+2 \times 19.2+(10-4)(19.2-9.81)=126.74 kN / m ^{2}

For Layer 2, p_{o}=126.74+2(19.2-9.81)+1 \times(18.24-9.81)=153.95 kN / m ^{2}

For Layer 3, p_{o}=153.95+1(18.24-9.81)+1.5 \times(20.0-9.81)=177.67 kN / m ^{2}

Computation of \Delta p=

For Layer 1

Area at 2 m depth below fictitious footing =(3.9+2) \times(3+2)=29.5 m ^{2}

 

\Delta p=\frac{2500}{29.5}=84.75 kN / m ^{2}

 

For Layer 2

Area at 5 m depth below fictitious footing =(3.9+5) \times(3+5)=71.2 m ^{2}

 

\Delta p=\frac{2500}{71.2}=35.1 kN / m ^{2}

 

For Layer 3

Area at 7.5 m below fictitious footing =(3.9+7.5) \times(3+7.5)=119.7 m ^{2}

 

\Delta p=\frac{2500}{119.7}=20.9 kN / m ^{2}

 

Settlement computation

 

Layer 1 S_{1}=\frac{4 \times 0.23}{1+0.80} \log \frac{126.74+84.75}{126.74}=0.113 m

 

Layer 2 S_{2}=\frac{2 \times 0.34}{1+1.08} \log \frac{153.95+35.1}{153.95}=0.029 m

 

Layer 3 S_{3}=\frac{3 \times 0.2}{1+0.7} \log \frac{177.67+20.9}{177.67}=0.017 m

 

Total =0.159 m \approx 16 cm.

15.27

Related Answered Questions