The data below refer to the sewer network in Fig. 13.18. Continue the calculations in Example 13.8 and hence determine a suitable diameter for the remaining sewers.
Sewer reference no. | Length (m) | Gradient | Impermeable area (km²) | Comments |
3 | 65 | 1 in 160 | 0.002 | Branch |
3.1 | 75 | 1 in 160 | 0.003 | Branch |
1.3 | 70 | 1 in 200 | 0.004 | Main sewer |
1.4 | 80 | 1 in 285 | 0.005 | Main sewer |
This question continues the calculations started in Example 13.8, which stopped at sewer 1.2. The remaining calculations are shown in Table STQ13.5. Note the following.
(a) Sewer 1.2 is a carrier sewer. The final t_{F} and t_{C} of 1.30 and 10.02 min repectively are not used for the design of this sewer, but are used to design sewer 1.3 where the t_{C} = 10.02 + 0.82 = 10.84 min.
(b) Sewer 3.0 is a branch, so the calculations effectively start afresh.
(c) Sewer 1.3 continues the calculations for the main branch. Since it is the first pipe downstream of branch 3.0/3.1, the longest of the upstream t_{C} values is used (i.e. 10.02, not 9.07 min). Its cumulative impermeable area is the total of everything upstream (= 0.021 km²). Note that the 0.450 m diameter pipe only just passes (Q_{\text {FULL }} = 0.230 > Q_P = 0.226 m ^3 / s). It could be argued that the rational method tends to overdesign so this is entirely satisfactory, or it could be argued that a larger – but more expensive – pipe should be used to allow for any future increase in flow.
(d) Sewer 1.4 obviously needs a larger diameter since it has an increased catchment area and a shallower gradient than sewer 1.3, which only just passed. Hence the calculations start with a 0.525 m pipe
Table STQ13.5 | ||||||||||||
1
Sewer ref. no. |
2
Sewer length L (m) |
3
Gradient |
4
Guessed diameter (m) |
5
Q_{FULL}
(m³/s) |
6
Mean flow velocity V(m/s) |
7
t_{F} = L/60V (min) |
8
t_{C}
(min) |
9
i (mm/h) |
10
A_{IMP} for each sewer (km²) |
11
ΣA_{IMP} (km²) |
12
Q_{P} = 0.278 i \Sigma A_{ IMP }
(m³/s) |
13
Comments |
1.2 | 90 | 1 in 300
0.33 m/100 m |
0.375 | 0.115 | 1.03 | 1.46 | (10.18) | None | (0.012) | 0.146 | Fail | |
0.450 | 0.190 | 1.15 | 1.30 | (10.02) | None | 0.146 | OK | |||||
3.0 | 65 | 1 in 160
0.63 m/100 m |
0.150 | 0.014 | 0.79 | 1.37 | 8.37 | 44.9 | 0.002 | 0.002 | 0.025 | Fail |
0.225 | 0.042 | 1.03 | 1.05 | 8.05 | 45.8 | 0.025 | OK | |||||
3.1 | 75 | 1 in 160
0.63 m/100 m |
0.225 | 0.042 | 1.03 | 1.21 | 9.26 | 42.4 | 0.003 | 0.005 | 0.059 | Fail |
0.300 | 0.090 | 1.23 | 1.02 | 9.07 | 42.9 | 0.060 | OK | |||||
1.3 | 70 | 1 in 200
0.50 m/100 m |
0.450 | 0.230 | 1.43 | 0.82 | 10.84 | 38.7 | 0.004 | 0.021 | 0.226 | OK |
1.4 | 80 | 1 in 285
0.35 m/100 m |
0.525 | 0.285 | 1.32 | 1.01 | 11.85 | 36.6 | 0.005 | 0.026 | 0.265 | OK |