Holooly Plus Logo

Question 13.SQ.5: The data below refer to the sewer network in Fig. 13.18. Con......

The data below refer to the sewer network in Fig. 13.18. Continue the calculations in Example 13.8 and hence determine a suitable diameter for the remaining sewers.

Sewer reference no. Length (m) Gradient  Impermeable area (km²) Comments
3 65 1 in 160 0.002 Branch
3.1 75 1 in 160 0.003 Branch
1.3 70 1 in 200 0.004 Main sewer
1.4 80 1 in 285 0.005 Main sewer
Figure 13.18
Step-by-Step
The 'Blue Check Mark' means that this solution was answered by an expert.
Learn more on how do we answer questions.

This question continues the calculations started in Example 13.8, which stopped at sewer 1.2. The remaining calculations are shown in Table STQ13.5. Note the following.

(a) Sewer 1.2 is a carrier sewer. The final t_{F}  and  t_{C} of 1.30 and 10.02 min repectively are not used for the design of this sewer, but are used to design sewer 1.3 where the t_{C} = 10.02 + 0.82 = 10.84 min.

(b) Sewer 3.0 is a branch, so the calculations effectively start afresh.

(c) Sewer 1.3 continues the calculations for the main branch. Since it is the first pipe downstream of branch 3.0/3.1, the longest of the upstream t_{C} values is used (i.e. 10.02, not 9.07 min). Its cumulative impermeable area is the total of everything upstream (= 0.021 km²). Note that the 0.450 m diameter pipe only just passes (Q_{\text {FULL }} = 0.230 > Q_P = 0.226  m ^3 / s). It could be argued that the rational method tends to overdesign so this is entirely satisfactory, or it could be argued that a larger – but more expensive – pipe should be used to allow for any future increase in flow.

(d) Sewer 1.4 obviously needs a larger diameter since it has an increased catchment area and a shallower gradient than sewer 1.3, which only just passed. Hence the calculations start with a 0.525 m pipe

Table STQ13.5
1

Sewer

ref. no.

2

Sewer

length

L

(m)

3

Gradient

4

Guessed

diameter

(m)

5

Q_{FULL}

(m³/s)

6

Mean

flow

velocity

V(m/s)

7

t_{F} =

L/60V

(min)

8

t_{C}

(min)

9

i

(mm/h)

10

A_{IMP} for

each

sewer

(km²)

11

ΣA_{IMP}

(km²)

12

Q_{P} = 0.278 i \Sigma A_{ IMP }

(m³/s)

13

Comments

1.2 90 1 in 300

0.33 m/100 m

0.375 0.115 1.03 1.46 (10.18) None (0.012) 0.146 Fail
0.450 0.190 1.15 1.30  (10.02) None 0.146 OK
3.0 65 1 in 160

0.63 m/100 m

0.150 0.014 0.79 1.37 8.37 44.9 0.002 0.002 0.025 Fail
0.225 0.042 1.03 1.05 8.05 45.8 0.025 OK
3.1 75 1 in 160

0.63 m/100 m

0.225 0.042 1.03 1.21 9.26 42.4 0.003 0.005 0.059 Fail
0.300 0.090 1.23 1.02 9.07 42.9 0.060 OK
1.3 70 1 in 200

0.50 m/100 m

0.450 0.230 1.43 0.82 10.84 38.7 0.004 0.021 0.226 OK
1.4 80 1 in 285

0.35 m/100 m

0.525 0.285 1.32 1.01 11.85 36.6 0.005 0.026 0.265 OK

Related Answered Questions