Question 16.2: Processing times (including setup times) and due dates for s...

Processing times (including setup times) and due dates for six jobs waiting to be processed at a work center are given in the following table. Determine the sequence of jobs, average flow time, average tardiness, and average number of jobs at the work center, for each of these rules:

a. FCFS

b. SPT

c. EDD

d. CR

Job Processing  Time (days) Due Date (days from present time)
A 2 7
B 8 16
C 4 4
D 10 17
E 5 15
F 12 18

Assume jobs arrived in the order shown.

The "Step-by-Step Explanation" refers to a detailed and sequential breakdown of the solution or reasoning behind the answer. This comprehensive explanation walks through each step of the answer, offering you clarity and understanding.
Our explanations are based on the best information we have, but they may not always be right or fit every situation.
The Blue Check Mark means that this solution has been answered and checked by an expert. This guarantees that the final answer is accurate.
Learn more on how we answer questions.

Related Answered Questions