Processing times (including setup times) and due dates for six jobs waiting to be processed at a work center are given in the following table. Determine the sequence of jobs, average flow time, average tardiness, and average number of jobs at the work center, for each of these rules:
a. FCFS
b. SPT
c. EDD
d. CR
Job | Processing Time (days) | Due Date (days from present time) |
A | 2 | 7 |
B | 8 | 16 |
C | 4 | 4 |
D | 10 | 17 |
E | 5 | 15 |
F | 12 | 18 |
Assume jobs arrived in the order shown.