Question 16.P.4: S/O rule. Using the following information , determine an ord...

S/O rule. Using the following information , determine an order processing sequence using tho S/O priority rule.

Order Processing Time Remaining (days) Due Date(days) Number of Operations Remaining
A 20 30 2
B 11 18 5
C 10 6 2
D 16 23 4