S/O rule. Using the following information , determine an order processing sequence using tho S/O priority rule.
Order | Processing Time Remaining (days) | Due Date(days) | Number of Operations Remaining |
A | 20 | 30 | 2 |
B | 11 | 18 | 5 |
C | 10 | 6 | 2 |
D | 16 | 23 | 4 |