Use the S/O rule to schedule the following jobs. Note that processing time includes the time remining for the current and subsequent operation. In additions, you will need to know the number of opertions remaining,including the current one.

Job Remaining Processing Time Due Date Remaining Number of Operations
A 4 14 3
B 16 32 6
C 8 8 5
D 20 34 2
E 10 30 4
F 18 30 2

 