Expected times in weeks and variances for the major activities of an R&D project are depicted in the following table. Determine the probability that project completion time will be

a. 50 weeks or less.
b. More than 50 weeks.

Path Activity Mean Variance
Top A 16 .69
B 11 .69
C 24 .11
Middle D 5 0
E 18 .25
F 26 .11
Bottom D 5 0
G 10 .25
H 14 .36
I 12 .11
Step-by-Step
The 'Blue Check Mark' means that this solution was answered by an expert.
Learn more on how do we answer questions.

Compute the mean and standard deviation for each path:

a. Compute the z for each path for the length specified. For any path that has a z of + 3.00 or more, treat its probability of completion before the specified time as 1.00. Use

z={\frac{50-t_{\mathrm{path}}}{\sigma_{\mathrm{path}}}}

The probability that each path will be completed in 50 weeks or less is shown in the corresponding diagram. (Probabilities are from Appendix B, Table B.) The probability that the project will be completed in 50 weeks or less depends on all three paths being completed in that time. Because z for the bottom path is greater than + 3.00, it is treated as having a probability of completion in 50 weeks of 100 percent. It is less certain that the other two paths will be completed in that time. The probability that both will not exceed 50 is the product of their individual probabilities of completion. Thus, .2061(.9525)(1.00) = .1963.

b. The probability that the project will exceed 50 weeks is the complement of this number, which is 1.000 – .1963 = .8037. (Note that it is not the product of the path probabilities.)

Path Expected Time (weeks) Standard Deviation (weeks)
Top 16+11+24=51 {\sqrt{.69+.69+.11}}=1.22
Middle 5+18+26=49 {\sqrt{.00+.25+.11}}=.60
Bottom 5+10+14+12=41 {\sqrt{.00+.25+.36+.11}}\;=.85

 

Table B 1. Areas under the standardized normal curve, from – ∞ to – z 
.09 .08 .07 .06 .05 .04 .03 .02 .01 .00 z
.0002 .0003 .0003 .0003 .0003 .0003 .0003 .0003 .0003 .0003 -3.4
.0003 .0004 .0004 .0004 .0004 .0004 .0004 .0005 .0005 .0005 -3.3
.0005 .0005 .0005 .0006 .0006 .0006 .0006 .0006 .0007 .0007 -3.2
.0007 .0007 .0008 .0008 .0008 .0008 .0009 .0009 .0009 .0010 -3.1
.0010 .0010 .0011 .0011 .0011 .0012 .0012 .0013 .0013 .0013 -3.0
.0014 .0014 .0015 .0015 .0016 .0016 .0017 .0018 .0018 .0019 -2.9
.0019 .0020 .0021 .0021 .0022 .0023 .0023 .0024 .0025 .0026 -2.8
.0026 .0027 .0028 .0029 .0030 .0031 .0032 .0033 .0034 .0035 -2.7
.0036 .0037 .0038 .0039 .0040 .0041 .0043 .0044 .0045 .0047 -2.6
.0048 .0049 .0051 .0052 .0054 .0055 .0057 .0059 .0060 .0062 -2.5
.0064 .0066 .0068 .0069 .0071 .0073 .0075 .0078 .0080 .0082 -2.4
.0084 .0087 .0089 .0091 .0094 .0096 .0099 .0102 .0104 .0107 -2.3
.0110 .0113 .0116 .0119 .0122 .0125 .0129 .0132 .0136 .0139 -2.2
.0143 .0146 .0150 .0154 .0158 .0162 .0166 .0170 .0174 .0179 -2.1
.0183 .0188 .0192 .0197 .0202 .0207 .0212 .0217 .0222 .0228 -2.0
.0233 .0239 .0244 .0250 .0256 .0262 .0268 .0274 .0281 .0287 -1.9
.0294 .0301 .0307 .0314 .0322 .0329 .0336 .0344 .0351 .0359 -1.8
.0367 .0375 .0384 .0392 .0401 .0409 .0418 .0427 .0436 .0446 -1.7
.0455 .0465 .0475 .0485 .0495 .0505 .0516 .0526 .0537 .0548 -1.6
.0559 .0571 .0582 .0594 .0606 .0618 .0630 .0643 .0655 .0668 -1.5
.0681 .0694 .0708 .0721 .0735 .0749 .0764 .0778 .0793 .0808 -1.4
.0823 .0838 .0853 .0869 .0885 .0901 .0918 .0934 .0951 .0968 -1.3
.0985 .1003 .1020 .1038 .1056 .1075 .1093 .1112 .1131 .1151 -1.2
.1170 .1190 .1210 .1230 .1251 .1271 .1292 .1314 .1335 .1357 -1.1
.1379 .1401 .1423 .1446 .1469 .1492 .1515 .1539 .1562 .1587 -1.0
.1611 .1635 .1660 .1685 .1711 .1736 .1762 .1788 .1814 .1841 -0.9
.1867 .1894 .1922 .1949 .1977 .2005 .2033 .2061 .2090 .2119 -0.8
.2148 .2177 .2206 .2236 .2266 .2296 .2327 .2358 .2389 .2420 -0.7
.2451 .2483 .2514 .2546 .2578 .2611 .2643 .2676 .2709 .2743 -0.6
.2776 .2810 .2843 .2877 .2912 .2946 .2981 .3015 .3050 .3085 -0.5
.3121 .3156 .3192 .3228 .3264 .3300 .3336 .3372 .3409 .3446 -0.4
.3483 .3520 .3557 .3594 .3632 .3669 .3707 .3745 .3783 .3821 -0.3
.3859 .3897 .3936 .3974 .4013 .4052 .4090 .4129 .4168 .4207 -0.2
.4247 .4286 .4325 .4364 .4404 .4443 .4483 .4522 .4562 .4602 -0.1
.4641 .4681 .4721 .4761 .4801 .4840 .4880 .4920 .4960 .5000 -0.0

 

Table B 2. Areas under the standardized normal curve, from – ∞ to + z   
z .00 .01 .02 .03 .04 .05 .06 .07 .08 .09
.0 .5000 .5040 .5080 .5120 .5160 .5199 .5239 .5279 .5319 .5359
.1 .5398 .5438 .5478 .5517 .5557 .5596 .5636 .5675 .5714 .5753
.2 .5793 .5832 .5871 .5910 .5948 .5987 .6026 .6064 .6103 .6141
.3 .6179 .6217 .6255 .6293 .6331 .6368 .6406 .6443 .6480 .6517
.4 .6554 .6591 .6628 .6664 .6700 .6736 .6772 .6808 .6844 .6879
.5 .6915 .6950 .6985 .7019 .7054 .7088 .7123 .7157 .7190 .7224
.6 .7257 .7291 .7324 .7357 .7389 .7422 .7454 .7486 .7517 .7549
.7 .7580 .7611 .7642 .7673 .7703 .7734 .7764 .7794 .7823 .7852
.8 .7881 .7910 .7939 .7967 .7995 .8023 .8051 .8078 .8106 .8133
.9 .8159 .8186 .8212 .8238 .8264 .8289 .8315 .8340 .8365 .8389
1.0 .8413 .8438 .8461 .8485 .8508 .8531 .8554 .8577 .8599 .8621
1.1 .8643 .8665 .8686 .8708 .8729 .8749 .8770 .8790 .8810 .8830
1.2 .8849 .8869 .8888 .8907 .8925 .8944 .8962 .8980 .8997 .9015
1.3 .9032 .9049 .9066 .9082 .9099 .9115 .9131 .9147 .9162 .9177
1.4 .9192 .9207 .9222 .9236 .9251 .9265 .9279 .9292 .9306 .9319
1.5 .9332 .9345 .9357 .9370 .9382 .9394 .9406 .9418 .9429 .9441
1.6 .9452 .9463 .9474 .9484 .9495 .9505 .9515 .9525 .9535 .9545
1.7 .9554 .9564 .9573 .9582 .9591 .9599 .9608 .9616 .9625 .9633
1.8 .9641 .9649 .9656 .9664 .9671 .9678 .9686 .9693 .9699 .9706
1.9 .9713 .9719 .9726 .9732 .9738 .9744 .9750 .9756 .9761 .9767
2.0 .9772 .9778 .9783 .9788 .9793 .9798 .9803 .9808 .9812 .9817
2.1 .9821 .9826 .9830 .9834 .9838 .9842 .9846 .9850 .9854 .9857
2.2 .9861 .9864 .9868 .9871 .9875 .9878 .9881 .9884 .9887 .9890
2.3 .9893 .9896 .9898 .9901 .9904 .9906 .9909 .9911 .9913 .9916
2.4 .9918 .9920 .9922 .9925 .9927 .9929 .9931 .9932 .9934 .9936
2.5 .9938 .9940 .9941 .9943 .9945 .9946 .9948 .9949 .9951 .9952
2.6 .9953 .9955 .9956 .9957 .9959 .9960 .9961 .9962 .9963 .9964
2.7 .9965 .9966 .9967 .9968 .9969 .9970 .9971 .9972 .9973 .9974
2.8 .9974 .9975 .9976 .9977 .9977 .9978 .9979 .9979 .9980 .9981
2.9 .9981 .9982 .9982 .9983 .9984 .9984 .9985 .9985 .9986 .9986
3.0 .9987 .9987 .9987 .9988 .9988 .9989 .9989 .9989 .9990 .9990
3.1 .9990 .9991 .9991 .9991 .9992 .9992 .9992 .9992 .9993 .9993
3.2 .9993 .9993 .9994 .9994 .9994 .9994 .9994 .9995 .9995 .9995
3.3 .9995 .9995 .9995 .9996 .9996 .9996 .9996 .9996 .9996 .9997
3.4 .9997 .9997 .9997 .9997 .9997 .9997 .9997 .9997 .9997 .9998
P17.4

Related Answered Questions

Question: 17.7

Verified Answer:

a. Determine which activities are on the critical ...
Question: 17.4

Verified Answer:

Either the starting times or the finishing times c...
Question: 17.3

Verified Answer:

We must add the LS and LF times to the brackets on...
Question: 17.2

Verified Answer:

Begin by placing brackets at the two ends of each ...
Question: 17.P.3

Verified Answer:

Standard deviations cannot be added, but variances...