Question 17.7: Using the following information, develop the optimal time–co......

Using the following information, develop the optimal time–cost solution. Project costs are $1,000 per day.

Activity Normal
Time
Crash
Time
Cost per Day to
Crash
a 6 6
b 10 8 $500
c 5 4 300
d 4 1 700
e 9 7 600
f 2 1 800
17.7
Step-by-Step
The 'Blue Check Mark' means that this solution was answered by an expert.
Learn more on how do we answer questions.

a. Determine which activities are on the critical path, its length, and the length of the other path:

b. Rank the critical path activities in order of lowest crashing cost, and determine the number of days each can be crashed. Note: Available days = Normal time – Crash time.

c. Begin shortening the project, one day at a time, and check after each reduction to see which path is critical. (After a certain point, another path may equal the length of the shortened critical path.) Thus:

(1) Shorten activity c one day at a cost of $300. The length of the critical path now becomes 19 days.
(2) Activity c cannot be shortened any more. Shorten activity e one day at a cost of $600. The length of path c-d-e-f now becomes 18 days, which is the same as the length of path a-b-f.
(3) The paths are now both critical; further improvements will necessitate shortening both paths.

The remaining activities for crashing and their costs are:

At first glance, it would seem that crashing f would not be advantageous, because it has the highest crashing cost. However, f is on both paths, so shortening f by one day would shorten both paths (and hence, the project) by one day for a cost of $800. The option of shortening the least expensive activity on each path would cost $500 for b and $600 for e, or $1,100. Thus shorten f by one day. The project duration is now 17 days.

(4) At this point, no additional improvement is feasible. The cost to crash b is $500 and the cost to crash e is $600, for a total of $1,100, and that would exceed the indirect project costs of $1,000 per day.

(5) The crashing sequence is summarized below:

Path Length
a-b-f 18
c-d-e-f 20 (critical path)

 

Activity Cost per Day to Crash Available Days
c $300 1
e 600 2
d 700 3
f 800 1

 

Path Activity Crash Cost (per day)
a-b-f a No reduction possible
b $500
f 800
c-d-e-f c No further reduction possible
d $700
e 600
f 800

 

LENGTH AFTER CRASHING n DAYS:
Path n = 0 1 2 3
a-b-f 18 18 18 17
c-d-e-f 20 19 18 17
Activity crashed c e f
Cost $300 $600 $800

Related Answered Questions

Question: 17.4

Verified Answer:

Either the starting times or the finishing times c...
Question: 17.3

Verified Answer:

We must add the LS and LF times to the brackets on...
Question: 17.2

Verified Answer:

Begin by placing brackets at the two ends of each ...
Question: 17.P.3

Verified Answer:

Standard deviations cannot be added, but variances...