The network diagram for a project is shown in the accompanying figure, with three time estimates for each activity. Activity times are in weeks. Do the following:

a. Compute the expected time for each activity and the expected duration for each path.
b. Identify the critical path.
c. Compute the variance of each activity and the variance and standard deviation of each path.

17.5 Q
Step-by-Step
The 'Blue Check Mark' means that this solution was answered by an expert.
Learn more on how do we answer questions.

a.

b. The path that has the longest expected duration is the critical path. Because path d-e-f has the largest path total, it is the critical path.

c.

TIMES
Path Activity t_{o} t_{m} t_{p} t_{e}\ =\frac{{t}_{o}\ +\ 4{t}_{m}\ +{t}_{p}}{6} Path Total
a-b-c a 1 3 4 2.83 \left. \begin{matrix}  \\ {}\\{} \\{}\\ {}\\ {}\\ {}\\ {} \end{matrix} \right \} 10.00
b 2 4 6 4.00
c 2 3 5 3.17
d-e-f d 3 4 5 4.00 \left. \begin{matrix}  \\ {}\\{} \\{}\\ {}\\ {}\\ {}\\ {} \end{matrix} \right \} 16.00
e 3 5 7 5.00
f 5 7 9 7.00
g-h-i g 2 3 6 3.33 \left. \begin{matrix}  \\ {}\\{} \\{}\\ {}\\ {}\\ {}\\ {} \end{matrix} \right \} 13.50
h 4 6 8 6.00
i 3 4 6 4.17
TIMES
Path Activity t_{o} t_{m} t_{p} \sigma^{2}{}_{a ct}\:=\:\frac{\left(t_{p}\,-\,t_{o}\right)^{2}}{36} \sigma^{2}{}_{\mathrm{path}} σ_{\text{path}}
a-b-c a 1 3 4 (4-1)^{2}/36=\ 9/36 \left. \begin{matrix}  \\ {}\\{} \\{}\\ {}\\ {}\\ {}\\ {} \end{matrix} \right \} 34/36=0.944 0.97
b 2 4 6 (6-2)^{2}/36=16/36
c 2 3 5 (5-2)^{2}/36=\ 9/36
d-e-f d 3 4 5 \begin{array}{c c}{{(5-3)^{2}/36=}}&{{4/36}}\end{array} \left. \begin{matrix}  \\ {}\\{} \\{}\\ {}\\ {}\\ {}\\ {} \end{matrix} \right \} 36/36=1.00 1.00
e 3 5 7 (7-3)^{2}/36=16/36
f 5 7 9 (9-5)^{2}/36=16/36
g-h-i g 2 3 6 (6-2)^{2}/36=16/36 \left. \begin{matrix}  \\ {}\\{} \\{}\\ {}\\ {}\\ {}\\ {} \end{matrix} \right \} 41/36=1.139 1.07
h 4 6 8 (8-4)^{2}/36=16/36
i 3 4 6 (6-3)^{2}/36=\ 9/36

Related Answered Questions

Question: 17.7

Verified Answer:

a. Determine which activities are on the critical ...
Question: 17.4

Verified Answer:

Either the starting times or the finishing times c...
Question: 17.3

Verified Answer:

We must add the LS and LF times to the brackets on...