Holooly Plus Logo

Question 17.1: Given the additional information on the bank network of Figu......

Given the additional information on the bank network of Figure 17.4 shown in Figure 17.5 , determine

a. The length of each path.
b. The critical path.
c. The expected length of the project.
d. The amount of slack time for each path.

Figure 17.4
figure 17.5
Step-by-Step
The 'Blue Check Mark' means that this solution was answered by an expert.
Learn more on how do we answer questions.

a. As shown in the following table, the path lengths are 18 weeks, 20 weeks, and 14 weeks.

b. Path 1-2-5-6 is the longest path (20 weeks), so it is the critical path.

c. The expected length of the project is equal to the length of the critical path (i.e., 20 weeks).
d. We find the slack for each path by subtracting its length from the length of the critical path, as shown in the last column of the table. (Note: It is sometimes desirable to know the slack time associated with activities. The next section describes a method for obtaining those slack times.)

Path Length (weeks) Slack
1-2-4-5-6 8 + 6 + 3 + 1 = 18 20 – 18 = 2
1-2-5-6 8 + 11 + 1 = 20* 20 – 20 = 0
1-3-5-6 4 + 9 + 1 = 14 20 – 14 = 6

*Critical path length.

Related Answered Questions

Question: 17.7

Verified Answer:

a. Determine which activities are on the critical ...
Question: 17.4

Verified Answer:

Either the starting times or the finishing times c...
Question: 17.3

Verified Answer:

We must add the LS and LF times to the brackets on...
Question: 17.2

Verified Answer:

Begin by placing brackets at the two ends of each ...
Question: 17.P.3

Verified Answer:

Standard deviations cannot be added, but variances...