A defense contractor in Dallas has six jobs awaiting processing. Processing time and due dates are given in the table. Assume that jobs arrive in the order shown. Set the processing sequence according to FCFS and evaluate. Start date is day 1.
JOB | JOB PROCESSING TIME (DAYS) |
JOB DUE DATE (DAYS) |
A | 6 | 22 |
B | 12 | 14 |
C | 14 | 30 |
D | 2 | 18 |
E | 10 | 25 |
F | 4 | 34 |