Question 15.EX.3: GANTT SCHEDULING CHART. First Printing in Winter Park, Flori...

GANTT SCHEDULING CHART. First Printing in Winter Park, Florida, wants to use a Gantt chart to show the scheduling of three orders, jobs A, B, and C.
APPROACH \blacktriangleright In Figure 15.4, each pair of brackets on the time axis denotes the estimated starting and finishing of a job enclosed within it. The solid bars reflect the actual status or progress of the job. We are just finishing day 5.