JOHNSON’S RULE. Five specialty jobs at a La Crosse, Wisconsin, tool and die shop must be processed through two work centers (drill press and lathe). The time for processing each job follows:
Work (processing) Time for Jobs (hours)
JOB | WORK CENTER 1 (DRILL PRESS) |
WORK CENTER 2 (LATHE) |
A | 5 | 2 |
B | 3 | 6 |
C | 8 | 4 |
D | 10 | 7 |
E | 7 | 12 |
The owner, Niranjan Pati, wants to set the sequence to minimize his total time for the five jobs.
APPROACH \blacktriangleright Pati applies the four steps of Johnson’s rule.