Question 15.EX.7: JOHNSON’S RULE. Five specialty jobs at a La Crosse, Wisconsi...

JOHNSON’S RULE. Five specialty jobs at a La Crosse, Wisconsin, tool and die shop must be processed through two work centers (drill press and lathe). The time for processing each job follows:

Work (processing) Time for Jobs (hours)

JOB WORK CENTER 1
(DRILL PRESS)
WORK CENTER 2
(LATHE)
A 5 2
B 3 6
C 8 4
D 10 7
E 7 12

The owner, Niranjan Pati, wants to set the sequence to minimize his total time for the five jobs.

APPROACH \blacktriangleright Pati applies the four steps of Johnson’s rule.

The "Step-by-Step Explanation" refers to a detailed and sequential breakdown of the solution or reasoning behind the answer. This comprehensive explanation walks through each step of the answer, offering you clarity and understanding.
Our explanations are based on the best information we have, but they may not always be right or fit every situation.
The Blue Check Mark means that this solution has been answered and checked by an expert. This guarantees that the final answer is accurate.
Learn more on how we answer questions.

Related Answered Questions