Use Johnson’s rule to find the optimum sequence for processing the jobs shown through two work centers. Times at each center are in hours.
JOB | WORK CENTER 1 | WORK CENTER 2 |
A | 6 | 12 |
B | 3 | 7 |
C | 18 | 9 |
D | 15 | 14 |
E | 16 | 8 |
F | 10 | 15 |
Use Johnson’s rule to find the optimum sequence for processing the jobs shown through two work centers. Times at each center are in hours.
JOB | WORK CENTER 1 | WORK CENTER 2 |
A | 6 | 12 |
B | 3 | 7 |
C | 18 | 9 |
D | 15 | 14 |
E | 16 | 8 |
F | 10 | 15 |