Question 15.SP.4: Use Johnson’s rule to find the optimum sequence for processi...

Use Johnson’s rule to find the optimum sequence for processing the jobs shown through two work centers. Times at each center are in hours.

JOB WORK CENTER 1 WORK CENTER 2
A 6 12
B 3 7
C 18 9
D 15 14
E 16 8
F 10 15
The Blue Check Mark means that this solution has been answered and checked by an expert. This guarantees that the final answer is accurate.
Learn more on how we answer questions.
B A F D C E

The sequential times are:

Work center 1 3 6 10 15 18 16
Work center 2 7 12 15 14 9 8