Question 15.EX.5: PRIORITY RULES FOR DISPATCHING. Five architectural rendering...

PRIORITY RULES FOR DISPATCHING. Five architectural rendering jobs are waiting to be assigned at Avanti Sethi Architects. Their work (processing) times and due dates are given in the following table. The firm wants to determine the sequence of processing according to (1) FCFS, (2) SPT, (3) EDD, and (4) LPT rules. Jobs were assigned a letter in the order they arrived. Today is day 1, and work begins today.

JOB JOBWORK
(PROCESSING) TIME
(DAYS)
JOB DUE
DATE
(DAYS)
A 6 8
B 2 6
C 8 18
D 3 15
E 9 23

APPROACH \blacktriangleright Each of the four priority rules is examined in turn. Four measures of effectiveness can be computed for each rule and then compared to see which rule is best for the company.

The Blue Check Mark means that this solution has been answered and checked by an expert. This guarantees that the final answer is accurate.
Learn more on how we answer questions.

SOLUTION \blacktriangleright
1. The FCFS sequence shown in the next table is simply A–B–C–D–E.

JOB SEQUENCE JOBWORK
(PROCESSING) TIME
FLOW
TIME
JOB DUE
DATE
JOB
LATENESS
A 6 6 8 0
B 2 8 6 2
C 8 16 18 0
D 3 19 15 4
E 9 28 23 5
28 77 11

The FCFS rule results in the following measures of effectiveness:

a. Average completion time = \frac{Sum  of  total  flow  time}{Number  of  jobs} = \frac{77  days}{5} = 15.4 days

b. Utilization metric = \frac{Total  job  work  (processing)  time}{Sum  of  total  flow  time} = \frac{28}{77} = 36.4%

c. Average number of jobs in the system = \frac{Sum  of  total  flow  time}{Total  job  work  (processing)  time} = \frac{77  days}{28  days} = 2.75 jobs

d. Average job lateness = \frac{Total  late  days}{Number  of  jobs} = \frac{11}{5} = 2.2 days

2. The SPT rule shown in the next table results in the sequence B–D–A–C–E. Orders are sequenced according to processing time, with the highest priority given to the shortest job.

JOB SEQUENCE JOBWORK
(PROCESSING) TIME
FLOW
TIME
JOB DUE
DATE
JOB
LATENESS
B 2 2 6 0
D 3 5 15 0
A 6 11 8 3
C 8 19 18 1
E 9 28 23 5
28 65 9

Measurements of effectiveness for SPT are:

a. Average completion time = \frac{65}{5} = 13 days

b. Utilization metric = \frac{28}{65} = 43.1%

c. Average number of jobs in the system = \frac{65}{28} = 2.32 jobs

d. Average job lateness = \frac{9}{5} = 1.8 days

3. The EDD rule shown in the next table gives the sequence B–A–D–C–E. Note that jobs are ordered by earliest due date first.

JOB SEQUENCE JOBWORK
(PROCESSING) TIME
FLOW
TIME
JOB DUE
DATE
JOB
LATENESS
B 2 2 6 0
A 6 8 8 0
D 3 11 15 0
C 8 19 18 1
E 9 28 23 5
28 68 6

Measurements of effectiveness for EDD are:

a. Average completion time = \frac{68}{5} = 13.6 days

b. Utilization metric = \frac{28}{68} = 41.2%

c. Average number of jobs in the system = \frac{68}{28} = 2.43 jobs

d. Average job lateness = \frac{6}{5} = 1.2 days

4. The LPT rule shown in the next table results in the order E–C–A–D–B.

JOB SEQUENCE JOBWORK
(PROCESSING) TIME
FLOW
TIME
JOB DUE
DATE
JOB
LATENESS
E 9 9 23 0
C 8 17 18 0
A 6 23 8 15
D 3 26 15 11
B 2 28 6 22
28 103 48

Measures of effectiveness for LPT are:

a. Average completion time = \frac{103}{5} = 20.6 days

b. Utilization metric = \frac{28}{103} = 27.2%

c. Average number of jobs in the system = \frac{103}{2} = 3.68 jobs

d. Average job lateness = \frac{48}{5} = 9.6 days

The results of these four rules are summarized in the following table:

RULE AVERAGE
COMPLETION
TIME (DAYS)
UTILIZATION
METRIC
(%)
AVERAGE NUMBER
OF JOBS IN
SYSTEM
AVERAGE
LATENESS
(DAYS)
FCFS 15.4 36.4 2.75 2.2
SPT 13.0 43.1 2.32 1.8
EDD 13.6 41.2 2.43 1.2
LPT 20.6 27.2 3.68 9.6

INSIGHT \blacktriangleright LPT is the least effective measurement for sequencing for the Avanti Sethi firm. SPT is superior in 3 measures, and EDD is superior in the fourth (average lateness).
LEARNING EXERCISE \blacktriangleright If job A takes 7 days (instead of 6), how do the 4 measures of effectiveness change under the FCFS rule? [Answer: 16.4 days, 35.4%, 2.83 jobs, 2.8 days late.]
RELATED PROBLEMS \blacktriangleright 15.15, 15.17a–d, 15.18, 15.19 (15.15 alternate, 15.24 are available in MyOMLab)
EXCEL OM Data File Ch15Ex5.xls can be found in MyOMLab.
ACTIVE MODEL 15.1 This example is further illustrated in Active Model 15.1 in MyOMLab.

Related Answered Questions